Attending the meeting were representatives of the leaders of agencies and units: Department of Construction, Department of Agriculture and Environment, Provincial Land Fund Development Center, Provincial People's Committee Office; related professional departments; representatives of the leaders of Project Management Board 2 - Ministry of Construction ; representatives of the leaders of the People's Committee, related professional departments of the communes: Khun Ha, Binh Lu, Ban Bo, Muong Khoa, Tan Uyen, Pac Ta, Muong Than.

At the meeting, representatives of the Department of Construction reported on the construction progress, compensation and site clearance work up to now; difficulties and obstacles in the implementation of the Project. Accordingly, the Project: Connecting traffic in the Northern mountainous provinces funded by the Asian Development Bank (ADB) and the Australian Government (the route connecting Lai Chau with the Noi Bai - Lao Cai expressway) with a total route length of 82.975 km. The compensation and site clearance work regularly received the direction of the Provincial Party Committee, the Provincial People's Committee and the Provincial People's Council, promptly approved the list of land acquisition, forest land conversion, and forest conversion as a legal basis for specialized agencies to implement.

The participation of local Party committees, authorities, specialized agencies, and socio -political organizations in coordinating propaganda, mobilization, and dissemination of policies and regimes, especially the support of affected people in the project area.

Up to this point, construction items and construction packages are continuing to be deployed. The total number of kilometers of handed over land has reached 99.72%. Currently, specialized units, Party committees and local authorities continue to strengthen propaganda and mobilization work to create consensus among the people when the State reclaims land and promptly hands over the construction site for the project.
Discussing at the meeting, representatives of departments, branches and localities focused on solutions to speed up the progress of compensation and site clearance; propaganda and mobilization work for people; project construction progress...

Concluding the meeting, Mr. Giang A Tinh - Vice Chairman of the Provincial People's Committee highly appreciated the efforts of departments, branches, units and localities in implementing the project. At the same time, he requested the communes to coordinate with specialized units and investors in propaganda and mobilization of people in compensation, support and resettlement. The contractor shall prepare construction plans for each day and each week; take advantage of favorable weather to deploy construction measures, ensuring construction progress according to plan.
Project Management Board 2 urges and directs the construction contractor to coordinate with the People's Committees of communes to resolve people's petitions to ensure stable life and cultivation of people; review intersections with residential roads, carry out safe connections; direct the contractor to concentrate human resources, machinery and equipment to speed up the construction progress of the project packages...