How is the 500 billion VND bridge to relieve traffic jams at the southern gateway of Ho Chi Minh City being implemented?

Báo Tiền PhongBáo Tiền Phong30/04/2024


TPO - The Rach Dia bridge project on Le Van Luong Street (connecting District 7 and Nha Be District) is being accelerated to complete by the end of this year, in order to reduce traffic congestion in the southern gateway area of ​​Ho Chi Minh City.

How is the 500 billion VND bridge to relieve traffic jams at the southern gateway of Ho Chi Minh City being implemented? Photo 1

Rach Dia Bridge connects the two ends of Nha Be district - District 7 (HCMC), construction began in July 2023. This bridge crosses the canal of the same name, with the hope that after completion, it will become a vital bridge, increasing the connectivity of Nha Be district and District 7.

How is the 500 billion VND bridge to relieve traffic jams at the southern gateway of Ho Chi Minh City being implemented? Photo 2

The Rach Dia bridge project above, with a total investment of more than 500 billion VND, is being accelerated to complete by the end of 2024, to replace the old, degraded iron bridge and reduce traffic congestion for the southern gateway area of ​​Ho Chi Minh City.

How is the 500 billion VND bridge to relieve traffic jams at the southern gateway of Ho Chi Minh City being implemented? photo 3

According to the design, the new Rach Dia bridge is 318m long, 9-10.5m wide, and has 9 spans. The two ends of the bridge are made of approach roads with a total length of 233m and width of 14-27m.

How is the 500 billion VND bridge to relieve traffic jams at the southern gateway of Ho Chi Minh City being implemented? photo 4

According to Project Management Board 4 - Management Board of Investment and Construction of Traffic Works in Ho Chi Minh City (Traffic Board), up to now, the project has completed nearly 50% of the volume.

How is the 500 billion VND bridge to relieve traffic jams at the southern gateway of Ho Chi Minh City being implemented? Photo 5
After many months of construction, the total progress of the entire project has reached nearly 50%. The bridge section across Rach Dia has completed 10/10 piers and 8/10 piers.
How is the 500 billion VND bridge to relieve traffic jams at the southern gateway of Ho Chi Minh City being implemented? Photo 6

Dozens of workers and many machines are also rushing to build the bridge's sections.

How is the 500 billion VND bridge to relieve traffic jams at the southern gateway of Ho Chi Minh City being implemented? Photo 7

The approach road section is completing the roadbed treatment, load-reducing floor, installing 95% of the drainage culverts, and currently continuing to construct the road foundation and retaining wall.

How is the 500 billion VND bridge to relieve traffic jams at the southern gateway of Ho Chi Minh City being implemented? Photo 8

The construction site is organizing 4 construction teams (3 on land and 1 underwater).

How is the 500 billion VND bridge to relieve traffic jams at the southern gateway of Ho Chi Minh City being implemented? Photo 9

Previously, the work of relocating technical infrastructure, compensation, support and resettlement for people was completed, and 100% of the site was handed over by the end of 2023.

How is the 500 billion VND bridge to relieve traffic jams at the southern gateway of Ho Chi Minh City being implemented? Photo 10

Some important items must be constructed in the middle of the canal, the contractor must use 2 large barges to bring machinery to the middle of the canal for construction.

How is the 500 billion VND bridge to relieve traffic jams at the southern gateway of Ho Chi Minh City being implemented? Photo 11

The new Rach Dia Bridge, once completed, will connect Le Van Luong Street directly to Nguyen Van Linh Street, becoming a vital bridge, increasing the connectivity of Nha Be District and District 7, helping to reduce the load on Rach Dia 2 Bridge on Nguyen Huu Tho Street, which is already overloaded and often congested during rush hours.

Duy Anh



Source

Comment (0)

No data
No data

Same tag

Same category

Western tourists enjoy buying Mid-Autumn Festival toys on Hang Ma Street to give to their children and grandchildren.
Hang Ma Street is brilliant with Mid-Autumn colors, young people are excitedly checking in non-stop
Historical message: Vinh Nghiem Pagoda woodblocks - documentary heritage of humanity
Admiring Gia Lai coastal wind power fields hidden in the clouds

Same author

Heritage

;

Figure

;

Enterprise

;

No videos available

News

;

Political System

;

Destination

;

Product

;