[Photo series] 'Revealing' Thong Nhat Bridge, the central axis road is accelerating construction

(DN) - According to the Dong Nai Province Construction Investment Project Management Board, up to now, the Bien Hoa City Central Axis Road Construction Project (now in Tran Bien Ward) from Vo Thi Sau Street to Dang Van Tron Street has been completed with the value of the packages reaching nearly 661/1,106 billion VND. Of which, Thong Nhat Bridge, the most important item of the project, has completed more than 75% of the volume.

Báo Đồng NaiBáo Đồng Nai16/10/2025

Let's see the image of Thong Nhat Bridge and the central axis road after nearly 3 years since the groundbreaking date:

The Bien Hoa City Central Axis Road Project has a total length of more than 5.4km, divided into 2 branches. Photo: Minh Tai
Bien Hoa City Central Axis Road Project has a total length of more than 5.4km, divided into 2 branches. Photo: Minh Tai
Branch 1 starts at the intersection with Vo Thi Sau Street, crosses Thong Nhat Bridge, crosses Cu Lao Hiep Hoa, runs along Dong Nai River to the end point intersecting with Dang Van Tron Street at An Hao Bridge intersection. Branch 1 is over 3.7km long, with the current construction volume reaching about 65%. Photo: Minh Tai
Branch 1 starts at the intersection with Vo Thi Sau Street, crosses Thong Nhat Bridge, crosses Cu Lao Hiep Hoa, runs along Dong Nai River to the end point at the intersection with Dang Van Tron Street at An Hao Bridge intersection. Branch 1 is more than 3.7km long, and the construction volume is currently about 65%. Photo: Minh Tai
Branch 2 (right side) is more than 1.7km long, construction has reached about 60%. Branch 2 has its starting point at the roundabout intersection with Branch 1 at Cu Lao Hiep Hoa, its ending point is at the intersection with Dang Van Tron Street at the intersection of the road at the beginning of Buu Hoa Bridge. Photo: Minh Tai
Branch 2 (right side) is more than 1.7km long, about 60% complete. Branch 2 starts at the roundabout intersection with Branch 1 at Cu Lao Hiep Hoa, and ends at Dang Van Tron Street at the intersection of Buu Hoa Bridge. Photo: Minh Tai
Thong Nhat Bridge across Cai River, connecting the central urban area with Cu Lao Hiep Hoa is the most important part of the project. Photo: Minh Tai
Thong Nhat Bridge across Cai River, connecting the central urban area with Hiep Hoa Islet, is the most important part of the project. Photo: Minh Tai
According to the design, Thong Nhat Bridge has a scale of 6-10 lanes, a width of 45-95m, a length of about 765m, of which the main bridge is 559m long. The current construction volume has reached nearly 360.3/479 billion VND, equivalent to more than 75%. Photo: Minh Tai
According to the design, Thong Nhat Bridge has a scale of 6-10 lanes, a width of 45-95m, a length of about 765m, of which the main bridge is 559m long. The current construction volume has reached nearly 360.3/479 billion VND, equivalent to more than 75%. Photo: Minh Tai
On the Hiep Hoa Islet side, there are still land issues for 3 households within the parallel road of the Thong Nhat Bridge. The locality is focusing on speeding up the compensation and site clearance work to hand over the remaining part in October 2025. Photo: Minh Tai
On the Hiep Hoa Islet side, there are still land issues for 3 households within the parallel road of the Thong Nhat Bridge. The locality is focusing on speeding up the compensation and site clearance work to hand over the remaining area in October 2025. Photo: Minh Tai
Previously, in mid-September, Tinh Hoi Pagoda (located on Cu Lao Hiep Hoa) handed over nearly 4,000 square meters of land to implement the Central Axis Road Project. Photo: Minh Tai
Previously, in mid-September, Tinh Hoi Pagoda (located on Hiep Hoa Islet) handed over nearly 4,000 square meters of land to implement the Central Axis Road Project. Photo: Minh Tai
In total, the project has 396 households whose land is subject to land acquisition with a total area of ​​nearly 34.4 hectares. Currently, the project construction area is more than 30.7 hectares, equivalent to more than 92% of the area. Photo: Minh Tai
In total, the project has 396 households whose land is subject to land acquisition with a total area of ​​nearly 34.4 hectares. Currently, the project construction area is more than 30.7 hectares, equivalent to more than 92% of the area. Photo: Minh Tai

Xuan Luong - Minh Tai

Source: https://baodongnai.com.vn/tin-moi/202510/chum-anh-lo-dien-cau-thong-nhat-duong-truc-trung-tam-dang-tang-toc-thi-cong-0751f43/


Comment (0)

No data
No data

Same tag

Same category

In the season of 'hunting' for reed grass in Binh Lieu
In the middle of Can Gio mangrove forest
Quang Ngai fishermen pocket millions of dong every day after hitting the jackpot with shrimp
Yen Nhi's national costume performance video has the highest views at Miss Grand International

Same author

Heritage

Figure

Enterprise

Hoang Thuy Linh brings the hit song with hundreds of millions of views to the world festival stage

News

Political System

Destination

Product