Terminal T3 of Tan Son Nhat Airport is 83% completed, operational on April 30, 2025

Báo Đầu tưBáo Đầu tư28/12/2024

The T3 terminal project at Tan Son Nhat Airport has completed more than 83% of the work volume and is in the process of completing the interior to put into operation on April 30, 2025.


Terminal T3 of Tan Son Nhat Airport is 83% completed, operational on April 30, 2025

The T3 terminal project at Tan Son Nhat Airport has completed more than 83% of the work volume and is in the process of completing the interior to put into operation on April 30, 2025.

On the afternoon of December 27, Airports Corporation of Vietnam (ACV) launched a 120-day and night competition to complete the T3 passenger terminal project at Tan Son Nhat Airport.

Panoramic view of Tan Son Nhat Airport Terminal 3 from above

According to ACV's report, as of December 27, the total volume of the Project has reached more than 83% and the expanded aircraft parking area has been put into operation.

Currently, the contractor is installing the electrical system, air conditioning and ventilation system, fire protection system, etc. According to the plan of Vietnam Airports Corporation, the entire project will be completed on April 30, 2025 (2 months ahead of schedule).

The rough part of the station has been completed, now contractors are installing the interior and finishing the exterior decoration.

To shorten the progress, the investor and contractor have applied many synchronous solutions to overcome difficulties in narrow construction sites, rainy weather and especially construction under conditions where Tan Son Nhat Airport is still operating normally.

Most contractors have responded to the Government 's call, working overtime, creating solutions to protect against rain and sun, applying advanced construction technologies, not succumbing to weather difficulties, in the spirit of overcoming the sun and rain.

The 2-storey overpass system in front of the station has completed the rough construction and is installing railings.

The project to build the T3 passenger terminal at Tan Son Nhat International Airport includes four main items: the passenger terminal, the multi-storey car park combined with non-aviation services, the overpass system in front of the terminal and the aircraft parking lot. The project has a total investment of 10,990 billion VND.

Once completed, the terminal will serve domestic flights with a capacity of 20 million passengers/year, meeting 7,000 passengers/peak hour. At that time, it will solve the congestion situation at Tan Son Nhat International Airport.



Source: https://baodautu.vn/nha-ga-t3-san-bay-tan-son-nhat-da-hoan-thanh-83-khai-thac-dip-3042025-d236282.html

Comment (0)

No data
No data

Same tag

Same category

Visit U Minh Ha to experience green tourism in Muoi Ngot and Song Trem
Vietnam team promoted to FIFA rank after victory over Nepal, Indonesia in danger
71 years after liberation, Hanoi retains its heritage beauty in the modern flow
71st anniversary of Capital Liberation Day - stirring up the spirit for Hanoi to step firmly into the new era

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product