The Depot station, which includes many different sections, has been completed. Train testing and emergency training are currently underway... the Nhon - Hanoi station metro line is expected to be operational in July this year.
Video : Panorama of the Nhon - Hanoi station metro line before it goes into operation.
Nhon Depot Station (Tay Tuu Ward, Bac Tu Liem District, Hanoi) of the Nhon - Hanoi Railway Station urban railway project has been completed. After more than 10 years of construction and more than 4 years of assembling train cars, many trains are running on trial.
With an area of 15 hectares, Nhon Depot - Hanoi Station includes works such as the operation building (OCC), train hangar, maintenance house, electrical engineering and other auxiliary works.
Image of the train hangar at the Depot station. Many trains are currently undergoing testing so they can be put into operation in July this year.
Maintenance and electrical engineering area...
Engineers and train maintenance workers. At the end of 2021, 10 trains of the Nhon - Hanoi station metro project arrived at the Depot. The trains are manufactured according to European standards, the manufacturer is Alstom (France).
The works at the Depot station are completed and are just waiting to be put into operation. The Depot project started on January 12, 2013, 7 years after the station was completed.
Train washing area. Nhon - Hanoi station metro trains are cleaned using French automatic washing technology, the entire train cleaning process takes only 3 minutes.
Operational area - OCC (including the operation, monitoring and command center of the entire Nhon - Hanoi railway station urban railway ) at Depot station.
Currently, the staff of Hanoi Metro Company Limited starts the trial operation at 7:45 and ends at 16:45 every day (except Saturday and Sunday).
The trial operation was supervised by a number of foreign experts.
Technical parameters at the Operation, Monitoring and Command Center of the entire Nhon - Hanoi Railway Station urban railway line (OCC).
The Nhon - Hanoi railway station urban railway section is 12.5 km long, passing through 8 elevated stations and 4 underground stations, of which the elevated section (Nhon - Cau Giay) is 8.5 km long and the underground section (Cau Giay - Hanoi station) is 4 km long.
After several delays in its operational plan, it is expected to serve passengers in July this year. The project's extension has increased costs, with the total proposed investment being VND34,530 billion, an increase of about VND4,905 billion compared to the original estimate.
Image inside Nhon station (S1).
Train driver test runs on Nhon - Hanoi station metro line. Previously, dozens of train drivers had many courses to operate this train.
To board the train, passengers use a plastic card or coin ticket. Each ticket can only be swiped once when the door opens.
Inside the Nhon - Hanoi station metro train. The train is fully equipped with amenities such as air conditioning, ventilation, passenger radio system, camera system, independent fire and smoke detection system, LED lights that automatically adjust the light accordingly when entering the underground section.
The interior of the train is mainly designed in light gray, the handrails for passengers standing on the carriage are red. On the train there are also priority areas reserved for the disabled, seats for the elderly, women and children.
The station areas along the metro line are decorated and have beautiful scenery.
The train also uses the CBTC (Communication-Based Train Control) signalling solution called URBALIS, which is Alstom's most advanced solution with advantages such as flexible control system structure; optimizing safety and ensuring uninterrupted service provision for passengers.
Image of train entering Nhon station (S1).
According to plan, the Nhon - Hanoi station metro train will be put into commercial operation from July this year.