On the afternoon of September 30, comrade Le Anh Quan, member of the Standing Committee of the City Party Committee, Permanent Vice Chairman of the City People's Committee inspected the implementation of the investment project to build a road connecting Provincial Road 354 through Kien Thuy Industrial Park to the coastal road; the progress of disbursement of public investment capital in 2025 managed by the Kien Thuy Regional Project Management Board and the implementation of 2-level local government in some localities.
Through a field survey of some sections of the provincial road 354 connection project and an inspection of the Kien Thuy Commune Public Administration Service Center, Mr. Le Anh Quan, Standing Vice Chairman of the City People's Committee, acknowledged and commended the efforts of the localities and the Kien Thuy Area Project Management Board in implementing the tasks.

The Standing Vice Chairman of the City People's Committee emphasized that in parallel with the implementation of two-level local government, with a large amount of work, units need to be determined and coordinate closely, especially in site clearance work to effectively implement key projects.

However, the progress of disbursement of public investment capital is still slow compared to the average of the whole city. In particular, the project of connecting Provincial Road 354 to the coastal road is a special project, lasting many years. Therefore, he requested the Kien Thuy Project Management Board to urgently speed up the progress and complete the construction in October. Contractors, especially Viet Uc and Phuong Dong contractors, must focus on construction. Kien Hung commune must soon complete the handover of the site to the investor.

For new rural projects, traffic and civil works need to be reviewed, accepted, settled and paid for; focus on processing and completing documents for school and cultural house projects.

With the Lao Cai - Hanoi - Hai Phong railway project, localities must urgently count and prepare resettlement plans, ready to implement when there is an official route.

Regarding the operation of the Public Administration Service Center, the Standing Vice Chairman of the City People's Committee suggested continuing to improve personnel, giving priority to local authorities, and flexibly signing short-term contracts. Localities need to review headquarters and equipment, ensuring the construction of a harmonious and modern working space, contributing to raising the rate of online records to 80% according to the general rate of the whole city.
Departments and branches coordinate to remove difficulties, adjust capital sources appropriately, and urge project settlement. The Department of Construction urgently synthesizes and protects plans related to the Lao Cai - Hanoi - Hai Phong railway project. The Department of Agriculture and Environment coordinates and guides localities to handle land-related problems. The Department of Finance guides the settlement of regular funding sources, ensuring general progress...

According to the Kien Thuy Regional Project Management Board, as of September 29, the disbursement value in Kien Thuy region reached 553.9/1,389.6 billion VND, equivalent to 39.86% of the plan. Of which, public investment capital reached 66.25%, model new rural area 58.84%, the project connecting provincial road 354 only reached 12.5%, only the Lao Cai - Hanoi - Hai Phong railway project has not yet disbursed.
Key projects are being focused on implementation. The road connecting Provincial Road 354 to the coastal road has reached more than 83% of the volume, currently there is still a household in Kien Hung commune that has not yet handed over the site. For 34 other public investment projects, the progress is 45 - 95%. The model new rural construction program with 124 basic traffic routes has been completed, with an average progress of 92%, many civil works reaching 60 - 98%.
Tan Trao Industrial Park Phase 1 project paid compensation of 145.3 billion VND to 299 households, reclaiming 30.56 hectares. Kien Thuy Project Management Board affirmed its determination to complete 100% capital disbursement by 2025.
After nearly 3 months of operating the 2-level government model in 5 communes Nghi Duong, Kien Thuy, Kien Hung, Kien Minh, Kien Hai, operations have been basically stable, with a high rate of receiving and processing documents. However, there are some difficulties related to land procedures, infrastructure, equipment, specialized management personnel and a rapidly increasing workload when many large projects are simultaneously implemented.
VAN NGA - LE DUNGSource: https://baohaiphong.vn/hoan-thanh-du-an-xay-dung-duong-noi-tinh-lo-354-den-duong-bo-ven-bien-trong-thang-10-522218.html