Vietnam.vn - Nền tảng quảng bá Việt Nam

Chau Doc - Can Tho Expressway Construction Contractor

Báo Giao thôngBáo Giao thông30/09/2024


Overcoming floods, speeding up construction

At the construction site of the Western Expressway, passing through An Giang province, Giao Thong Newspaper reporters recorded hundreds of workers and dozens of pieces of equipment and machinery working every day.

Nhà thầu thi công cao tốc Châu Đốc - Cần Thơ - Sóc Trăng chạy đua với lũ ĐBSCL- Ảnh 1.

The contractor proactively divided and constructed the flood-proof section of the Chau Doc - Can Tho - Soc Trang expressway project, passing through An Giang province.

At package 42, Lieutenant Colonel Nguyen Thanh Nhang, Deputy Director of Truong Son 11 Management Board, Truong Son Construction Corporation, said that the construction unit will construct nearly 14km of the highway section passing through An Giang province. Of which, about 4km is in the flood-risk area.

To proactively respond, the contractor organized workers to construct these locations before the flood flooded the fields.

Currently, all the piers and piers of the 5 bridges in the package have been completed and the girders are being installed. The surface of these bridges is expected to be basically completed by mid-December. Many other items of these bridges are also targeted for completion this year.

Nhà thầu thi công cao tốc Châu Đốc - Cần Thơ - Sóc Trăng chạy đua với lũ ĐBSCL- Ảnh 2.

Contractors speed up construction progress of the Western expressway.

For road locations in flooded areas, contractors proactively construct across the flood and workers are currently installing wicks.

"The construction site receives 2,000m3 of sand per day, focusing on bringing it to key locations and locations at risk of flooding for construction first. The purpose is that when floods flood the fields, the construction will not be affected.

Currently, these positions have basically overcome the flood, workers are working continuously and throughout to speed up progress," said Lieutenant Colonel Nhang.

Bring more workers to the construction site in October

According to Lieutenant Colonel Nhang, the construction progress is currently over 25%, 0.5% higher than planned. To achieve this result, the contractor was very determined.

"We have organized workers to work two shifts, starting from 7am to 11pm, an additional 4 hours compared to normal working hours. It is expected that in October, the contractor will add 60 more workers to the construction site," said Mr. Nhang.

Nhà thầu thi công cao tốc Châu Đốc - Cần Thơ - Sóc Trăng chạy đua với lũ ĐBSCL- Ảnh 3.

Many sections of the Western highway, passing through An Giang province, have been waterproofed.

Mr. Tran Minh Khang, technical officer of Tan Nam Construction Joint Stock Company (construction contractor) said that the package No. 45 implemented by the company is 5.3km long and has 3 bridges. Up to now, the construction progress has reached 26%.

At the construction site, the contractor is having workers drill bored piles, cement soil piles, make piers, cast beams and install waterproof wicks.

The company arranged 100 workers with 22 machines and equipment. Workers were organized to work 3 shifts with 6 construction sites, starting from 7am to 11pm the same day.

Nhà thầu thi công cao tốc Châu Đốc - Cần Thơ - Sóc Trăng chạy đua với lũ ĐBSCL- Ảnh 4.

Workers work overtime at the Chau Doc - Can Tho - Soc Trang expressway construction site, through An Giang province.

The Management Board of Investment Projects for Construction of Traffic and Agricultural Works of An Giang Province (investor) said that the Chau Doc - Can Tho - Soc Trang Expressway, the section passing through the province, has four packages including: 42, 43, 44 and 45. Total output is currently reaching nearly 30%, ahead of schedule.

The Chau Doc - Can Tho - Soc Trang Expressway Project Phase 1 has a total length of 188.2km passing through 4 provinces and cities: An Giang, Can Tho, Hau Giang and Soc Trang.
The starting point connects National Highway 91 in Chau Doc city (An Giang) and the end point intersects with Nam Song Hau National Highway, connecting to Tran De port access road (Soc Trang), with a total investment of 44,691 billion VND. The entire route is expected to be completed and put into use in 2027.
Of which, component project 1 in An Giang province is 57.2km long, component project 2 in Can Tho city is 37.2km long, component project 3 in Hau Giang province is nearly 37km long and component project 4 in Soc Trang province is 56.9km long.
In phase 1, the project will be invested in a 4-lane scale, with a design speed of 100km/h. In the completed phase, the project will be invested in a 6-lane scale.



Source: https://www.baogiaothong.vn/nha-thau-thi-cong-cao-toc-chau-doc-can-tho-soc-trang-chay-dua-voi-lu-dbscl-192240930162857113.htm

Comment (0)

No data
No data

Same tag

Same category

Spend millions to learn flower arrangement, find bonding experiences during Mid-Autumn Festival
There is a hill of purple Sim flowers in the sky of Son La
Lost in cloud hunting in Ta Xua
The beauty of Ha Long Bay has been recognized as a heritage site by UNESCO three times.

Same author

Heritage

;

Figure

;

Enterprise

;

No videos available

News

;

Political System

;

Destination

;

Product

;