Deputy Prime Minister Nguyen Hoa Binh inspected and requested the competent authorities and investors to focus on removing difficulties and speeding up the progress of the Khanh Hoa - Buon Ma Thuot expressway.
On November 23, Deputy Prime Minister Nguyen Hoa Binh inspected the situation and progress of the Khanh Hoa - Buon Ma Thuot Expressway Project. He was accompanied by Deputy Minister of Transport Le Anh Tuan and the investor of the project component 3.
Deputy Prime Minister Nguyen Hoa Binh inspected the progress of the Khanh Hoa - Buon Ma Thuot Expressway Project, component project 3. Photo: NH
At the construction site, reporting to the Deputy Prime Minister, the Dak Lak Provincial Management Board of Investment Projects for Construction of Transport Works and Rural Development (representing the investor) said that the Khanh Hoa - Buon Ma Thuot Expressway is divided into 3 component projects. Component project 1, managed by the Khanh Hoa Provincial People's Committee, is 31.5km long and scheduled to be completed in 2026.
Component 2, managed by the Ministry of Transport, is 36.9km long and is scheduled to be completed in 2027. Component 3, managed by the People's Committee of Dak Lak province, is 48km long and is scheduled to be completed in 2026.
According to the plan, by August 30, 2025, the progress of component project 3 will be open to traffic. Photo: NH
Regarding site clearance (GPMB), as of October 30, the total volume of site clearance and handover work reached more than 99% (equivalent to 48.09/48.09km). Currently, there is only 1ha of drainage canal outside the main route being implemented for GPMB because it has just been added to the land use planning of Cu Kuin district.
The relocation of technical infrastructure (electricity, water, telecommunications, etc.) is being implemented by localities. Regarding the dumping site for excess materials, according to the investor's assessment, it basically meets the demand, in which some locations belonging to component projects 2 and 3 are completing procedures to be used for the project.
To date, the construction volume has reached more than 26% of the contract value. Of which, package 1 has achieved more than 31%; package 2 has achieved more than 23% of the contract value; package 3 has achieved more than 29% of the contract value. According to the investor, the project progress is being accelerated by contractors, completed as planned, meeting the set schedule.
During the inspection, the Deputy Prime Minister presented gifts to the construction contractors. Photo: NH
Deputy Prime Minister Nguyen Hoa Binh highly appreciated the Ministry of Transport, Dak Lak province, and Khanh Hoa province for their efforts in mobilizing resources and overcoming difficulties to implement the project investment.
At the same time, we highly appreciate the investor, contractors, officers, engineers, workers and laborers who have worked actively and continuously to speed up the construction progress, striving to complete ahead of schedule for each construction item and the entire project.
The Deputy Prime Minister requested the competent authorities and investors to focus on removing current difficulties of the project, and give more drastic direction to speed up the construction progress, while ensuring project quality, labor safety, and environmental sanitation.