Despite difficult terrain conditions, with deep water flooding on many roads, the shock team supporting the Yen The Regional Power Management Team, Bac Ninh Power Company, is still working day and night to ensure absolute safety for people and equipment, while gradually restoring power to residential areas and essential infrastructure in the area.
After 1 day of urgent deployment, by 9:30 p.m. on October 8, the working teams had restored power to 7/10 medium voltage lines, 274/398 transformer stations, bringing power back to serve more than 25,000 customers in the Yen The Power Management Team area. The remaining areas are still being monitored by power workers, waiting for the water level to recede to ensure safety before re-energizing.
According to Bac Ninh Electricity Company, in the work of overcoming the consequences of storms and floods, safety criteria are given top priority. Electricity management teams closely coordinate with local authorities, police and militia forces to isolate dangerous areas, warn people not to go near broken electric poles, transformer stations and downed electric wires.
At the same time, the unit also stepped up propaganda on mass media and social networks, advising people not to arbitrarily restore electricity in flooded areas, and only use electrical equipment after it has been checked for safety.
Currently, officers and workers of Bac Ninh Electricity Company are still on duty 24/24, taking advantage of favorable weather to restore the power grid in the remaining areas affected and damaged by floods. The unit's goal is to bring the entire power grid in the province back into operation, ensuring safe and continuous power supply to the people as soon as conditions allow.
Source: https://baotintuc.vn/kinh-te/hon-25000-khach-hang-tai-khu-vuc-yen-the-bac-ninh-co-dien-tro-lai-20251009132644504.htm