New inspiration for transport infrastructure breakthroughs

Việt NamViệt Nam04/09/2024


Construction pace at most expressway projects is being pushed to maximum speed during the peak period of 500 days and nights of competition to complete 3,000 km of expressway - an important goal set out in the Resolution of the 13th National Congress of the Party.

Construction of Road Tunnel No. 3, Quang Ngai – Hoai Nhon Expressway Project

Even faster

Ten days after Prime Minister Pham Minh Chinh launched a peak emulation campaign of 500 days and nights to complete 3,000 km of expressway (August 18, 2024), the pace at the construction site of Package XL03, Quang Ngai - Hoai Nhon Component Project of the North - South Expressway Construction Project in the East phase 2021 - 2025 has been pushed to a new level.

The 88-km-long Quang Ngai – Hoai Nhon component project with a total investment of VND21,000 billion is the largest project among the 12 component projects of the North-South Eastern Expressway in the 2021-2025 period.

In particular, Package XL03 is undertaken by Deo Ca Group with the highlight of building a 3,200 m long road tunnel, located between the two provinces of Quang Ngai and Binh Dinh. This item is the progress critical path, deciding whether the Quang Ngai - Hoai Nhon Component Project can be completed by December 2025 or not.

Under the scorching late summer sun of over 40 degrees Celsius in the South Central region, the construction units of Road Tunnel No. 3 started working at 6:00 a.m. to finish the first shift at around 11:00 a.m. The break of over 1 hour and 30 minutes was a precious time for the workers to quickly have lunch and take a short nap in the public houses near the construction site before starting the afternoon shift, which lasted until late at night.

It should be added that the mechanical teams, despite having to work outdoors in the scorching heat to prepare the hundreds of tons of tunnel lining formwork, still feel much more comfortable than the engineers and workers working at the construction site of Road Tunnel No. 3.

Even though they don't have to work outdoors and are constantly pumped with fresh air, the air in the tunnel is always thick, noisy, and very humid, making it like a "stew pot." Normal people will feel tightness in the chest and suffocation after standing for a while.

Deep inside the tunnel, workers operating drilling machines patiently trimmed the tunnel face flat, before drilling hundreds of holes into the hard rock layer for blasting. The working atmosphere at the construction site was bustling in accordance with the Prime Minister 's directive: "If it's urgent, then it's even more urgent."

Along with the addition of specialized equipment and skilled technicians, to speed up the construction progress of road tunnel No. 3, Deo Ca Group also boldly improved the construction organization method by dividing the tunnel into many small tunnels, combining inclined face excavation and spraying reinforcement immediately after excavation.

Mr. Bui Hong Dang, Director of the Tunnel Command Board of the Quang Ngai - Hoai Nhon Component Project (Deo Ca Group) said that this solution aims to shorten construction time and increase the load-bearing safety of the construction structure, overcoming the design with a shape that is not optimal in terms of the tunnel's load-bearing capacity.

Thanks to the increased force and the application of innovative construction methods, as of the end of August 2024, the progress of the road tunnel No. 3 is being significantly accelerated compared to the investor's requirements. The left tunnel has been dug 1,500 m/3,200 m, the right tunnel has been dug 1,619 m/3,200 m.

“We are organizing construction in 3 shifts, 4 crews around the clock, expected to dig the tunnel in March 2025, about 8 months ahead of the contract schedule, and together with other units, open the Quang Ngai - Hoai Nhon expressway to traffic in December 2025, nearly 6 months ahead of the general schedule,” said Mr. Dang.

Not only in Package XL03, the accelerated construction pace has appeared in most highway construction projects invested by the Ministry of Transport (MOT) and localities.

At the Khanh Hoa – Buon Ma Thuot Expressway Component 3 Project, Son Hai Group is focusing on maximum equipment and human resources to complete the work items signed with the investor 3 – 6 months ahead of schedule.

In addition, Son Hai Group also committed to completing 52 km of Bien Hoa - Vung Tau Expressway in 2025, 12 months ahead of schedule, determined to set a new record in progress, and committed to being the leading enterprise in construction quality.

“We have seen the image of the Prime Minister attached to the highway with inspection trips and on-site instructions mostly on holidays, Saturdays and Sundays. That image has inspired us, the contractors and workers, to be more determined to complete the assigned tasks, to build highways that ensure progress and quality,” said Mr. Le Viet Hai, Chairman of Son Hai Group.

"Throughout holidays, through days off"

According to Mr. Nguyen Danh Huy, Deputy Minister of Transport, implementing the Resolution of the 13th National Party Congress, right from the beginning of the term, the Government has resolutely directed all levels, sectors and localities to synchronously deploy many solutions to promote investment in transport infrastructure projects to achieve important and outstanding results.

To date, the country has completed about 1,000 km of expressways, passing through 15 provinces and cities, bringing the total number of expressways to nearly 2,100 km; over 1,700 km are under construction, and about 1,400 km are about to start construction. The projects span across 48 provinces and cities across the country.

Even during the National Day holiday of September 2, workers across the country have 4 days off, but all contractors on expressway projects, especially the North-South expressway component projects in the 2021-2025 period deployed in the Central region, still work in 3 shifts, 4 teams, taking advantage of the last dry season weeks of 2024 to speed up progress.

On average, over the past 3 years, each year the country has put into operation about 300 km of highway, equal to the previous 10 years combined.

“Regular site inspections, including the Prime Minister's cross-country and Tet inspections and meetings of the State Steering Committee for important national and key projects in the transport sector, have promptly resolved difficulties and obstacles, creating momentum and determination among construction units. The leaders of the Ministry of Transport also continuously monitor the construction site to promptly resolve difficulties and speed up construction progress,” said Mr. Nguyen Danh Huy.

However, the goal of completing the remaining 1,000 km of highway within 500 days and nights is still a huge challenge, forcing the transport industry to accelerate even more.

Specifically, in addition to the 2,021 km that have been put into operation, there are currently about 1,700 km of expressway under construction, of which nearly 1,200 km are planned to be completed by 2025. Among the projects planned to be completed in 2025, nearly 700 km (belonging to 13 projects/component projects) basically meet the schedule; the remaining more than 300 km need drastic direction and the removal of many difficulties and obstacles to be completed in 2025.

In the latest directive issued on August 28, Minister of Transport Nguyen Van Thang himself requested Deputy Ministers of Transport, according to their assigned tasks, to actively urge and direct investors/project management boards to proactively work with localities to complete the target of 3,000 km of expressway by 2025, especially projects behind schedule.

The pressure to put the expressways into operation soon from the Government and the Ministry of Transport is becoming a driving force helping many contractors and investors overcome their own limits to complete the projects.

The sense of honor, professional pride and the future ahead motivates contractors to overcome difficulties. Many contractors accept “playing big”, willing to reduce profits to add manpower and equipment to shorten construction progress.

Top leaders of contractors are often present at the site, especially for packages that are critical to progress. In addition to the task of maintaining cash flow into packages in the final stages of construction, many top leaders of contractors also directly take care of mid-shift meals for workers and give bonuses to construction teams with good progress.

Mr. Pham Van Khoi, General Director of Phuong Thanh Construction Company - one of the main contractors of the Bung - Van Ninh Expressway Project, said that the contractor has mobilized enough human resources and equipment for the flood season before the rainy season begins.

“The capital is always available, the payment time has been shortened to the maximum, if the weather conditions are favorable, we will disburse more than the capital plan and progress plan registered with the investor - Project Management Board 6”, Mr. Khoi emphasized.

To support contractors during the 500-day and night peak competition, the Minister of Transport requested project management boards and investors of expressway projects to be proactive and urge localities to remove difficulties and obstacles in site clearance, relocation of technical infrastructure, and supply of construction materials; to concentrate, be highly determined, make great efforts, and resolutely carry out construction with the spirit of "overcoming the sun and overcoming the rain", "only working, not backing down", "3 shifts, 4 shifts", "eating quickly, sleeping urgently", "through holidays, Tet, and days off", "doing what needs to be done", "having committed, must be done; having promised, must be done" to speed up the progress of project implementation.

The urgent task at this time is to direct and urge contractors to focus on constructing items that are critical to progress such as tunnels, large bridges; areas that must be loaded, and weak ground treatment...

“The spirit is to make more efforts, be more determined, more resolute, focus on key points; closely direct, clearly assign people, tasks, time, progress, completion deadline, and have specific products,” the head of the transport sector requested.

Source: https://baodautu.vn/nguon-cam-hung-moi-cho-mui-dot-pha-ha-tang-giao-thong-d223908.html


Comment (0)

No data
No data

Same tag

Same category

Spend millions to learn flower arrangement, find bonding experiences during Mid-Autumn Festival
There is a hill of purple Sim flowers in the sky of Son La
Lost in cloud hunting in Ta Xua
The beauty of Ha Long Bay has been recognized as a heritage site by UNESCO three times.

Same author

Heritage

;

Figure

;

Enterprise

;

No videos available

News

;

Political System

;

Destination

;

Product

;