Re-planning of Lien Chieu wharf area, Da Nang

Báo Giao thôngBáo Giao thông24/03/2025

Lien Chieu wharf area (belonging to Da Nang seaport) will be planned to accommodate container, liquid/gas and bulk cargo.


In the Detailed Planning Report for the development of land and seaport areas in Da Nang for the period 2021-2030, with a vision to 2050, submitted by the Vietnam Maritime Administration and Waterways to the Ministry of Construction , Lien Chieu wharf area has been specifically proposed to meet the needs of various types of goods.

Quy hoạch lại khu bến Liên Chiểu, Đà Nẵng- Ảnh 1.

Perspective of Lien Chieu port project.

Accordingly, Lien Chieu port area plans container terminals, general cargo terminals, bulk cargo terminals, liquid/gas terminals and public service terminals, barge terminals with a capacity of up to 100,000 tons or larger when qualified.

Goods passing through the port area fluctuate from 8.7 - 13.7 million tons. The port scale will be from 5 - 8 newly built ports (including 5 - 8 wharves) with a total length of 1,380 - 2,780m and 1 bulk cargo port with a total length of 100m, 3 specialized buoy wharves relocated in accordance with the investment progress at Lien Chieu port area in the period of 2030 (not including other ports).

Specifically, the container port will plan 2-4 wharves (including 2-4 wharves) with a total length of 750-1,650m, receiving ships with a capacity of up to 100,000 tons or larger when qualified.

Of which, 2 start-up ports can handle 7.5 - 11.9 million tons of goods; the remaining 2 ports will develop to meet international container transit needs.

Liquid/gas cargo ports serving LNG and LPG storage are planned to have 1-2 ports (including 1-2 wharves) with a total length of 250 - 750m, receiving ships with a capacity of up to 100,000 tons or larger when qualified, meeting the need for cargo throughput from 0.45 - 0.75 million tons.

For buoy wharves and transshipment anchorage areas at Lien Chieu wharf area, relocation will be carried out in sync with the investment process of container ports at Lien Chieu wharf area.

At the same time, investing in 2 liquid cargo ports (including 2 wharves) with a total length of 380m to receive ships with a capacity of 30,000 tons will replace the liquid cargo ports when relocated, meeting the need for goods passing from 0.75 - 1.05 million tons.

According to the detailed planning of seaports, harbors, wharves, buoys, water areas, and water regions for the period 2021 - 2030, with a vision to 2050 approved by the Prime Minister , Lien Chieu port area has 2 - 4 ports (including 2 - 4 wharves).

Of which, 2 starting ports will handle 7.5 - 11.9 million tons of goods, the remaining 2 ports will develop to meet the needs of international container transit.



Source: https://www.baogiaothong.vn/quy-hoach-lai-khu-ben-lien-chieu-da-nang-192250324162322744.htm

Comment (0)

No data
No data

Same tag

Same category

There is a hill of purple Sim flowers in the sky of Son La
Lantern - A Mid-Autumn Festival gift in memory
Tò he – from a childhood gift to a million-dollar work of art
Efforts to preserve the traditional Mid-Autumn toy making craft in Ong Hao village

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product