Speeding up to the finish line of the first 20km of Khanh Hoa - Buon Ma Thuot highway

Overcoming difficult weather conditions, contractors are mobilizing maximum human resources and equipment to speed up construction to complete items of the Khanh Hoa - Buon Ma Thuot expressway project.

Báo Sài Gòn Giải phóngBáo Sài Gòn Giải phóng16/10/2025

Exciting atmosphere at the construction site of Khanh Hoa - Buon Ma Thuot Expressway. By: HIEU GIANG

On October 16, Mr. Pham Van Hoa, Deputy Director of the Khanh Hoa Provincial Department of Agriculture and Transport Construction Investment Project Management Board (investor of component project 1 of the Khanh Hoa - Buon Ma Thuot Expressway project), said that the project's progress is meeting requirements. The first 20km of the route is expected to be completed on December 19, 2025, according to the Prime Minister's direction.

cao tốc Khánh Hòa - Buôn Ma Thuột
The section of the Khanh Hoa - Buon Ma Thuot expressway project passing through Hoa Tri commune, Khanh Hoa province. Photo: HIEU GIANG

From May 2025 to now, the erratic sunshine and rain at the construction site have affected the construction progress, especially construction packages 2 and 3. To overcome the difficulties, the investor has directed the contractor to mobilize machinery, equipment, and human resources to organize construction in "3 shifts, 4 teams" to meet the progress.

dasua-7328.jpg
cao tốc Khánh Hòa - Buôn Ma Thuột
Workers of Son Hai Group Company Limited are constructing safety and noise protection railings at the beginning of the expressway. Photo: HIEU GIANG
cao tốc Khánh Hòa - Buôn Ma Thuột
Construction Package No. 1, executed by Son Hai Group Co., Ltd., has so far reached 78.85% of the contract value, exceeding the plan by 2.41%. Photo: HIEU GIANG
cao tốc Khánh Hòa - Buôn Ma Thuột
Construction Package No. 1 has 20km registered within the 3,000km expressway to be completed by the end of 2025 under the direction of the Prime Minister . Photo: HIEU GIANG
cao tốc Khánh Hòa - Buôn Ma Thuột
In the scorching midday sun, hundreds of engineers and workers are busy constructing. Photo: HIEU GIANG
cao tốc Khánh Hòa - Buôn Ma Thuột
Construction of median strips using automatic equipment with quality standards. Photo: HIEU GIANG
dasua-0031.jpg
Seamless concrete separator pouring machine helps save construction time and increase productivity. Photo: HIEU GIANG

Mr. Vu Huu Khoa, Deputy Director of Khanh Hoa Road Management and Construction Joint Stock Company, said that in construction package No. 1 (the first 22km section of the route), there are 9 bridges that the unit undertakes to construct.

To date, the unit has basically completed 8 bridges, and the Song Cai Bridge is expected to be completed in November this year, 3 months ahead of the contract schedule. The contractor is making efforts to mobilize machinery and equipment to speed up the progress.

cao tốc Khánh Hòa - Buôn Ma Thuột
Song Cai Bridge is constructed by Khanh Hoa Road Construction and Management Joint Stock Company. Photo: HIEU GIANG
cao tốc Khánh Hòa - Buôn Ma Thuột
The bridge girder is 38m long and weighs 72 tons. This is the last bridge in construction package No. 1. Photo: HIEU GIANG
cao tốc Khánh Hòa - Buôn Ma Thuột
The DT6 overpass on the highway is gradually taking shape. Photo: HIEU GIANG

Component 1 of the Khanh Hoa - Buon Ma Thuot Expressway project has 3 construction packages; the total value implemented to date is about 2,275 billion VND, reaching 62.86% of the contract value, exceeding the plan by 3.19%.

In addition to the 22km construction package No. 1 constructed by Son Hai Group Company Limited, the construction package No. 2 (10km in the middle of the route) implemented by the Phuong Nam - Bac Trung Nam - Dong Duong Joint Venture has so far reached 45.58% of the contract value; the construction package No. 3 (construction of Km30 bridge and Cua Dong bridge) implemented by Truong Son Construction Corporation has so far reached 51% of the contract value.

The Khanh Hoa - Buon Ma Thuot Expressway Project Phase 1 has a total length of 117.5km, a scale of 4 lanes, and a roadbed width of 17m. When completed, it will shorten the distance from Khanh Hoa province to the administrative - political center of Dak Lak province from about 200km to 117km.

Source: https://www.sggp.org.vn/tang-toc-ve-dich-20km-dau-tuyen-cao-toc-khanh-hoa-buon-ma-thuot-post818374.html


Comment (0)

No data
No data

Same tag

Same category

In the season of 'hunting' for reed grass in Binh Lieu
In the middle of Can Gio mangrove forest
Quang Ngai fishermen pocket millions of dong every day after hitting the jackpot with shrimp
Yen Nhi's national costume performance video has the highest views at Miss Grand International

Same author

Heritage

Figure

Enterprise

The 'neatest' market in Vietnam

News

Political System

Destination

Product