Close-up of Hanoi metro super project, delayed 13 times, trains still in storage

Báo Tiền PhongBáo Tiền Phong02/07/2024


TPO - The project has been behind schedule for 9 years and missed 13 times, but according to Tien Phong reporter on July 2, the project with a total investment of more than 30,000 billion VND is still exposed to the sun and rain, the trains are in storage.

CLIP Nhon - Hanoi metro depot is deserted, trains are lying still in the warehouse

Close-up of Hanoi metro super project, missed 13 times, trains still waiting in stock photo 1

June 30 was the deadline that the Prime Minister requested the Chairman of the Hanoi People's Committee to directly resolve the problems to put the trains into operation, but this progress has not been achieved.

Close-up of Hanoi metro super project, delayed 13 times, trains still waiting in stock photo 2

On the morning of July 2, it was noted that the entire elevated railway project from Cau Giay to Nhon was devoid of trains. This is the 13th time the project has missed its appointment with the people of Hanoi.

Close-up of Hanoi metro super project, missed 13 times, trains still waiting in stock photo 3

Many items and equipment, especially rails and elevators, have peeled paint, protective layer and rusted due to being exposed to the sun and rain for a long time.

Close-up of Hanoi metro super project, missed 13 times, trains still waiting in stock photo 4

At Nhon depot (Bac Tu Liem district), although it is a place for stopping, departing and turning around when trains operate on the route, there were no trains operating this morning.

Close-up of Hanoi metro super project, missed 13 times, trains still waiting in stock photo 5

The entire 15-hectare Nhon depot area was quiet on the morning of July 2.

Close-up of Hanoi metro super project, delayed 13 times, trains still lined up photo 6

Most of the trains are lying idle in warehouses and hangars.

Close-up of Hanoi metro super project, missed 13 times, trains still waiting in stock photo 7

Meanwhile, traffic on Highway 32 from Nhon to Cau Giay and vice versa is crowded with personal vehicles, constantly causing congestion and making travel difficult.

Close-up of Hanoi metro super project, missed 13 times, trains still lined up photo 8

Nhon - Hanoi station train during a test run on the project track.

Close-up of Hanoi metro super project, missed 13 times, trains still lined up photo 9

The project investor, the Hanoi Urban Railway Management Board (MRB), said that 10 trains of the project have completed the trial run and have been granted license plates by the Vietnam Register for operation. However, the project is currently being evaluated, appraised and accepted by specialized agencies, so the trains can only operate after this work is completed.

Construction started in September 2010 and was scheduled to be completed in 2015, but after 14 years of construction (9 years behind schedule, 13 missed deadlines), the urban railway still cannot carry passengers. The most recent missed deadline was June 30.

Currently, the Nhon - Hanoi Railway Station Metro project is also the project with the highest capital increase among the urban railway projects that have been and are being constructed in Hanoi. Specifically, according to the approved investment level at the time of commencement of the project, the cost was 18,408 billion VND (mainly ODA loans from the French Government ). Up to now, after several requests for adjustment, the total investment has increased to over 30,000 billion VND, an increase of nearly 63%.

Previously, the Cat Linh - Ha Dong urban railway line was 6 years behind schedule, 45% over budget, and missed deadlines 10 times.

News Reporter Group



Source: https://tienphong.vn/can-canh-sieu-du-an-metro-ha-noi-lo-hen-13-lan-tau-van-xep-kho-post1651367.tpo

Comment (0)

No data
No data

Same tag

Same category

Re-enactment of the Ly Dynasty's Mid-Autumn Festival at Thang Long Imperial Citadel
Western tourists enjoy buying Mid-Autumn Festival toys on Hang Ma Street to give to their children and grandchildren.
Hang Ma Street is brilliant with Mid-Autumn colors, young people are excitedly checking in non-stop
Historical message: Vinh Nghiem Pagoda woodblocks - documentary heritage of humanity

Same author

Heritage

;

Figure

;

Enterprise

;

No videos available

News

;

Political System

;

Destination

;

Product

;