Vietnam.vn - Nền tảng quảng bá Việt Nam

Hoang Huu Nam Road Project: 2km not completed after 9 years due to land acquisition issues

Báo Tuổi TrẻBáo Tuổi Trẻ30/06/2024


Nhiều đoạn đường Hoàng Hữu Nam (TP Thủ Đức) đã hoàn thành cơ bản, trải nhựa, bó vỉa - Ảnh: GIAI THỤY

Many sections of Hoang Huu Nam Street (Thu Duc City) have been basically completed, paved, and have sidewalks - Photo: GIAI THUY

According to the People's Committee of Thu Duc City (HCMC), the Hoang Huu Nam road project has a total length of 2km, connecting many important areas such as the new Eastern bus station, Hanoi highway intersection, Oncology Hospital 2...

The project started in June 2015, but was later halted due to site clearance issues. The project will not restart until 2023.

Talking to Tuoi Tre Online , the Thu Duc Area Construction Investment Management Board (investor) said that the units are actively mobilizing people to hand over the site and carry out "rolling" construction - the site is being worked on as it is developed, striving to complete by April 30, 2025.

Up to now, only more than 60% of the construction has been completed. Of which, the D400 and D13 areas have been completed to serve the Oncology Hospital and the new Eastern Bus Station. The section on Hoang Huu Nam Street is being worked on at locations where people have handed over the land.

100% of households in Long Thanh My and Tan Phu wards have agreed to receive money and hand over the land. The main problem with the land is currently 39 households in the project to expand the city's Martyrs' Cemetery.

Therefore, the Compensation and Site Clearance Board and the People's Committee of Thu Duc City have increased their efforts to mobilize people to hand over the site for completion of construction.

"We will work on the locations that have been handed over by the people first. There are places that have not been handed over but have enough land to build roads (not including sidewalks), so we can mobilize to continue working on them in the near future. Everyone's spirit is to strive to complete and inaugurate the road by April 30, 2025," said the representative.



Source: https://tuoitre.vn/du-an-duong-hoang-huu-nam-2km-lam-9-nam-chua-xong-do-vuong-mat-bang-20240630135111319.htm

Comment (0)

No data
No data

Same tag

Same category

Vietnam team promoted to FIFA rank after victory over Nepal, Indonesia in danger
71 years after liberation, Hanoi retains its heritage beauty in the modern flow
71st anniversary of Capital Liberation Day - stirring up the spirit for Hanoi to step firmly into the new era
Flooded areas in Lang Son seen from a helicopter

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product