Hai Duong speeds up construction progress to upgrade Cao Xa station cargo yard

Việt NamViệt Nam25/03/2024

dji_0023.jpg
Cao Xa Station (Cam Giang) will become an international transit station in the future. Currently, the project is in the interim implementation phase.
dji_0029.jpg
During this phase, at Cao Xa station, the freight yard within the railway land boundary will be renovated and upgraded to meet the minimum requirements for a specialized bonded yard.
dsc_7583.jpg
Construction items include renovating an 80 m2 office building, customs services, a 5,400 m2 cargo yard with lighting, water supply and drainage systems, surveillance cameras and fire prevention and fighting, and renovating the car road to the yard.
dsc_7585.jpg
Platform paving workers
dsc_9336.jpg
Construction of main terminal area
dji_0003-1-.jpg
Up to now, the construction of the cargo yard area has reached 80% of the volume.
dsc_7593-8ba8c237a33cabbf8124c6d6c1a6034d.jpg
The railway traffic barrier has also been completed. The construction unit strives to basically complete the items in the interim phase by April 15 so that the first international train can soon depart from Cao Xa station.

Cao Xa Station at km 50+ 870 belongs to the Hanoi - Hai Phong railway line, close to industrial parks such as Dai An, Cam Dien, Phuc Dien, Tan Truong... Vietnam Railway Corporation proposed to invest about 61 billion VND in phase 1 (not including site clearance) to carry out the following items: Renovating the current cargo yard surface, ensuring a cargo yard area of ​​10,000 m2; building a warehouse (temporary warehouse); building protective fences, surveillance camera systems, fire fighting systems, lighting in the cargo yard area...

THANH CHUNG - HA NGA

Source

Comment (0)

No data
No data

Same tag

Same category

Re-enactment of the Ly Dynasty's Mid-Autumn Festival at Thang Long Imperial Citadel
Western tourists enjoy buying Mid-Autumn Festival toys on Hang Ma Street to give to their children and grandchildren.
Hang Ma Street is brilliant with Mid-Autumn colors, young people are excitedly checking in non-stop
Historical message: Vinh Nghiem Pagoda woodblocks - documentary heritage of humanity

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product