Song Hong 4 Power Construction Joint Stock Company is the contractor from column 276 to column 283 in Tan Hong and Thuc Khang communes (Binh Giang) with a length of nearly 3.1km. This is the longest anchorage of the line in Hai Duong. The contractor has mobilized maximum human and material resources to carry out the construction with the determination to complete the wire pulling of the anchorage within 14 days...
The 500kV line 3 project from Quang Trach to Pho Noi, passing through Hai Duong, is nearly 31 km long, including 74 column foundation locations in 4 districts of Hai Duong: Ninh Giang, Gia Loc, Thanh Mien and Binh Giang. As of May 22, the contractor has completed all 74 column foundation locations, completed 47 locations, is constructing 15 locations, and has not yet installed 12 locations. According to the Prime Minister 's direction, the entire line must be completed in June 2024.
Up to this point, the 500kV line project, circuit 3, from Quang Trach to Pho Noi, has completed pulling 10/513 anchor intervals and is currently pulling 7/513 anchor intervals...
The 500 kV line project, circuit 3, Quang Trach - Pho Noi, once completed, will help reduce the load and avoid overloading of existing 500 kV lines, contributing to supplementing capacity from power sources in the North Central region to the load center in the Northern region...
THANH HOASource
Comment (0)