New Year's Day on Dong Dang - Tra Linh Highway

Cao Bang - At the Dong Dang - Tra Linh highway construction site, workers are still working hard.

Báo Lao ĐộngBáo Lao Động29/01/2025

Busy on the first highway through Cao Bang . Photo: Tan Van.

The Dong Dang - Tra Linh Expressway project has a total length of 121 km, divided into two phases. Phase 1, the Dong Dang - Tra Linh Expressway is invested with a length of more than 93 km, starting at the Tan Thanh Border Gate intersection, Van Lang district ( Lang Son ), and ending at the National Highway 3 intersection in Chi Thao commune, Quang Hoa district (Cao Bang). The highlight of the project is the two tunnels through the mountains of Dong Khe and That Khe.

Phase 1 of the project has a total investment of 14,167 billion VND, invested by the consortium of Deo Ca Group Joint Stock Company - ICV Vietnam Investment and Construction Joint Stock Company - Deo Ca Transport Infrastructure Investment Joint Stock Company - Construction Joint Stock Company 568. It is expected that phase 1 will be opened to traffic in 2025 and completed in 2026.

A view of the project from above. Photo: Tan Van.

In Thach An district (Cao Bang), there are 2 priority construction sites: km66+500, Don Lap village, Le Lai commune and tunnel 2 - km72, Thuy Hung commune. These construction sites concentrate a lot of workers and high-capacity machinery.

With 99% of the land in Cao Bang province, contractors are actively and urgently constructing with the spirit of "overcoming the sun, overcoming the rain", "3 shifts, 4 crews", mobilizing more than 1,000 personnel and over 370 machines and equipment to deploy 26 construction points in all categories of roads, bridges, tunnels and culverts.

Workers in tunnels through rocky mountains. Photo: Tan Van.

Currently, Dong Khe tunnel has opened both tubes, 3 months ahead of schedule. The contractor is pouring concrete for the tunnel lining, creating the roadbed inside the tunnel and installing equipment.

Having worked with Deo Ca Group for more than 2 years on large and small projects, Mr. Nguyen Van Thanh (from Ha Trung district, Thanh Hoa province) shared: "Every year, the group takes good care of the workers, so even though they have to be away from home and work through Tet, everyone is still very excited."

According to Mr. Thanh, on the first day of Tet this year, some workers are taking a temporary break, on the second day of Tet, everyone will return to their old work rhythm.

Workers work through Tet. Photo: Tan Van.

After more than 2 years away from home during Tet, putting aside the joy of family reunion during the New Year, Mr. Thanh is a bit proud that his wife has taken care of everything for his 3 children at home.

Besides the encouragement from Deo Ca Group and his wife and children in his hometown, local leaders also regularly care for and encourage workers working directly at the construction site.

Previously, on January 24-25, Chairman of the Provincial People's Committee Hoang Xuan Anh and Secretary of the Cao Bang Provincial Party Committee Quan Minh Cuong visited, encouraged and gave gifts to workers who worked through Tet.

Cao Bang Provincial Party Secretary Quan Minh Cuong visited and wished happy new year to workers who worked through Tet. Photo: Vu Tiep.

Cao Bang provincial leaders all acknowledged and commended the investor and contractor for their efforts during the construction process, ensuring the progress of the expressway project.

"In the last days of the year, our employees worked very urgently, following the spirit of 'overcoming the sun and overcoming the rain' initiated by the Prime Minister . The company also encouraged workers to stay and work through Tet to strive to open the route by the end of 2025.

Busy first days of the new year. Photo: Tan Van.

Regarding the workers' lives during Tet, what is at home is the same at the construction site. We organize Chung cake wrapping, peach blossoms, kumquat trees and traditional Tet dishes so that our brothers can enjoy the spring but not forget their duties, trying to keep up with the schedule," said the investor representative.

Laodong.vn

Source: https://laodong.vn/xa-hoi/ngay-dau-nam-tren-cao-toc-dong-dang-tra-linh-1456361.ldo


Comment (0)

No data
No data

Same tag

Same category

Spend millions to learn flower arrangement, find bonding experiences during Mid-Autumn Festival
There is a hill of purple Sim flowers in the sky of Son La
Lost in cloud hunting in Ta Xua
The beauty of Ha Long Bay has been recognized as a heritage site by UNESCO three times.

Same author

Heritage

;

Figure

;

Enterprise

;

No videos available

News

;

Political System

;

Destination

;

Product

;