Vietnam.vn - Nền tảng quảng bá Việt Nam

Nghe An: Proposal to temporarily restrict vehicles carrying wet sand from circulating through the construction area of ​​the National Highway 7 upgrade project

Recently, on Highway 7, there have been many large trucks carrying wet sand continuously, causing water and sand to spill onto the road surface. This has seriously affected the construction of the crushed stone base layer, the asphalt concrete paving plan and potentially poses a risk to traffic safety and environmental sanitation.

Báo Đại biểu Nhân dânBáo Đại biểu Nhân dân21/10/2025

Project Management Board 4 (Vietnam Road Administration) has just sent a document to the Provincial People's Committee and Nghe An Provincial Police, reporting on the construction status of the project to renovate and upgrade National Highway 7, section Km0 - Km36, and handling landslides caused by storms and floods in the Khe Thoi - Nam Can section; at the same time, proposing to temporarily restrict vehicles carrying wet sand from circulating through the construction area.

It is known that the National Highway 7 upgrade project was approved by the Ministry of Transport on March 18, 2022 and officially started construction in September 2022. The project has a total investment of more than 1,300 billion VND with a total length of 27.5 km passing through Dien Chau, Yen Thanh and Do Luong districts (old) of Nghe An province. The project is divided into 3 construction packages 01, 02 and 03. The packages are expected to be completed in December 2023. However, when the deadline came, the project could not be completed as planned. The Ministry of Transport then extended the deadline.
Despite being extended many times, the project is still behind schedule, greatly affecting traffic and the lives of households along the route.

According to Project Management Board 4, thanks to the active direction and support of the Provincial People's Committee, the Provincial Police and local authorities, the handover of the site has achieved positive results so far. The communes of Hop Minh, Van Tu and Minh Chau have completed 100% of the handover of the site; in Dien Chau commune, there are only two households still in dispute over land, waiting for the court's resolution.

Contractors are speeding up progress, organizing many construction teams simultaneously, striving to complete the asphalt concrete pavement in October 2025. However, according to the reflection of Project Management Board 4, recently, many large trucks carrying wet sand have been circulating on the route continuously, causing water and sand to spill onto the road surface. This seriously affects the construction process of the crushed stone aggregate base layer, the asphalt concrete pavement plan and poses a potential risk to traffic safety and environmental sanitation.

According to the plan, from October 14 to 25, 2025, contractors will deploy road paving from Km21+00 - Km25+00 in Van Tu commune. To ensure the quality of the project, the road surface needs to be kept dry and dust-free before being watered with asphalt. With the current situation of wet sand trucks circulating, the technical requirements cannot be met.

Based on that reality, Project Management Board 4 proposed that the Provincial People's Committee and Nghe An Provincial Police direct the functional forces to temporarily not allow wet sand trucks to circulate through the Van Tu commune section from October 14 to 30, 2025, in order to create conditions for construction units to complete the asphalt concrete paving project on schedule, ensuring the quality and aesthetics of the project.

This is the situation that has been happening on National Highway 7A for a long time, causing public outrage because the risk of traffic insecurity is always at a high level.
Not only sand trucks, but also oversized and overloaded vehicles are circulating densely on this highway. This has been a situation that has caused public outrage over the past time because the risk of traffic insecurity is always at a high level.

Project Management Board 4 expressed its wish to continue receiving attention and close direction from the leaders of the Provincial People's Committee and Nghe An Provincial Police so that the National Highway 7 Project can be completed soon, promoting investment efficiency, meeting the requirements of developing traffic infrastructure in the Western region of Nghe An.

Source: https://daibieunhandan.vn/nghe-an-kien-nghi-tam-thoi-han-che-xe-cho-cat-uot-luu-thong-qua-khu-vuc-thi-cong-du-an-cai-tao-nang-cap-quoc-lo-7-10391258.html


Comment (0)

No data
No data

Same tag

Same category

Stunningly beautiful terraced fields in Luc Hon valley
'Rich' flowers costing 1 million VND each are still popular on October 20th
Vietnamese Films and the Journey to the Oscars
Young people go to the Northwest to check in during the most beautiful rice season of the year

Same author

Heritage

Figure

Enterprise

Young people go to the Northwest to check in during the most beautiful rice season of the year

News

Political System

Destination

Product