Also attending were representatives of leaders of relevant departments, units, localities, Construction Investment Project Management Board No. 2 and Lam Dong Provincial People's Committee Office.

According to the report of the Phan Thiet Area Construction Investment Project Management Board, by October 10, 2025, the unit had disbursed 246,757 million VND, reaching nearly 32% of the capital plan for 2025. In the past time, the unit has proactively reviewed and proposed capital reduction adjustments for a number of newly started projects that have not fully used up the reserve fee or have no disbursement volume. Or in the case of a project with a large capital allocation that is currently stuck with compensation and clearance work, so the site cannot be handed over for construction, the project has been finalized but still has remaining capital...

After the Department of Finance and the People's Committee of Lam Dong province agreed to adjust the capital plan down, the Phan Thiet Area Construction Investment Project Management Board committed to disbursing the assigned public investment capital according to the direction of the Chairman of the Provincial People's Committee. Specifically, by the end of 2025, it will accelerate the progress of project implementation to reach 90% of the capital plan, while striving to continue to increase the disbursement rate until January 31, 2026.

At the meeting, representatives of departments, branches and localities discussed, contributed ideas and proposed solutions to remove current obstacles, focusing on a number of key projects such as: Repairing and upgrading Nguyen Dinh Chieu Street and Huynh Thuc Khang Street (section from Hoang Ngoc Tourist Area to Lang Chai intersection); Centralized wastewater treatment of Mui Ne National Tourist Area; Residential area south of Le Duan Street; Route 2, Hung Long service - park - resettlement area.

In his concluding remarks, Vice Chairman of the Provincial People's Committee Nguyen Minh highly appreciated the efforts of the Phan Thiet Area Construction Investment Project Management Board in disbursing public investment capital. However, he also pointed out that there are still many projects that have not met the schedule due to compensation, site clearance and other subjective reasons.

The goal is to ensure that public investment disbursement in 2025 reaches 100% of the plan, contributing to the successful implementation of the province's socio-economic targets, meeting the requirements of the Prime Minister.
Vice Chairman of the Provincial People's Committee Nguyen Minh
The Vice Chairman of the Provincial People's Committee requested the Project Management Board to proactively coordinate with relevant departments, units and localities to focus on removing difficulties and overcoming existing problems to speed up the implementation progress. As for projects and works that are favorable and have no problems, they will continue to speed up the construction progress earlier than expected.
In addition, the provincial People's Committee leaders also assigned relevant functional departments and localities to support, guide, and advise competent authorities to consider and resolve the problems as mentioned above. Especially regarding site clearance (specific land prices, compensation, support, resettlement), reviewing and adjusting reasonable capital, examining and approving investment settlement for project completion, creating conditions for resolving capital disbursement dossiers for investors...
Source: https://baolamdong.vn/pho-chu-tich-ubnd-tinh-lam-dong-lam-dong-lam-viec-voi-ban-quan-ly-du-an-dau-tu-xay-dung-so-2-ve-giai-ngan-dau-tu-cong-395667.html