New playground is picky

Việt NamViệt Nam02/07/2024


Many large enterprises that submitted bids for rest stops on the Eastern North-South Expressway have quietly withdrawn because they realized it was not easy to make a profit in this new, highly specialized business field.

 

Shaping the leading investor

“We are working closely with project management boards to speed up negotiations with investors. We aim to sign contracts for four investment projects to build and operate rest stops on the Eastern North-South Expressway by early July 2024,” said Mr. Nguyen Quang Giang, Deputy Director of the Vietnam Expressway Administration (Ministry of Transport).

In principle, the winning bid price remains unchanged, so negotiations with investors only revolve around minimizing the progress of public works to serve the essential needs of people and vehicles participating in traffic on the route.

According to Mr. Nguyen Quang Giang, this is not a simple task, because according to the bidding documents for investment projects to build rest stops on the North-South Expressway, the overall implementation progress is only 15 months, of which the time to complete public service works is 12 months.

The public works category, providing free services at rest stops on the North-South Expressway that the winning investor is required to invest in and build within 12 months from the date of signing the contract is also very large, including parking lots; resting spaces; temporary rest rooms for drivers; restrooms; information centers; places to organize and launch propaganda on traffic safety; and places for rescue workers and first aid for traffic accidents.

Previously, after a period of acceleration, the Vietnam Expressway Administration also approved the results of selecting investors for four investment projects to build and operate rest stops on the North-South Eastern Expressway. These four projects include: rest stop Km90+900 of the Cam Lam - Vinh Hao Component Project; rest stop Km144+560 of the Vinh Hao - Phan Thiet Component Project; rest stop Km329+700 of the Mai Son - National Highway 45 Component Project; rest stop Km47+500 of the Phan Thiet - Dau Giay Component Project.

Surprisingly, up to 3/4 of the investment projects to build and operate the above-mentioned rest stops belong to the joint venture of Phuong Trang Passenger Transport Joint Stock Company - Thanh Hiep Phat Company Limited (abbreviated as Phuong Trang - Thanh Hiep Phat joint venture). These are the rest stop at Km90+900 of the Cam Lam - Vinh Hao Component Project; the rest stop at Km144+560 of the Vinh Hao - Phan Thiet Component Project; the rest stop at Km47+500 of the Phan Thiet - Dau Giay Component Project.

The total cost that the Phuong Trang - Thanh Hiep Phat joint venture must spend to build the above 3 rest stops (including money paid to the state budget, compensation, support, and resettlement) is about 900 billion VND.

The initial victory of the Phuong Trang - Thanh Hiep Phat joint venture did not come easily, because all 3 component projects that this joint venture won the bid for had a very high level of competition. Even the Investment Project for Construction and Operation of Rest Stop Km47+500 under the Phan Thiet - Dau Giay Component Project, in addition to the Phuong Trang - Thanh Hiep Phat joint venture, had up to 6 investor consortia submitting bidding documents, among which were very strong units.

To select an investor with capacity and experience in operating rest stops, the bidding documents also require that the investor or consortium member must have been in business or operating specialized road services in the project under consideration and meet one of two conditions: having a decision to announce a type 1 rest stop put into operation; having a decision to announce a type 2, 3 or 4 rest stop put into operation, but must ensure that the rest stop has an area for inspection, maintenance, repair of vehicles and a fuel station (with supporting documents).

In case the above 2 criteria are not met, the investor or member of the consortium must have been in business and operated at least 2 services: motor vehicle repair and maintenance workshop or road traffic rescue and rescue center and petrol, oil fuel station or electric car charging station. At the same time, there must be at least one service in 3 services: parking lot, food, beverage, product sales; accommodation.

Compared with the above criteria, the Phuong Trang - Thanh Hiep Phat joint venture has many advantages, because Phuong Trang (FUTA Bus Lines) is a very large passenger transport brand in the South, owning a number of large, well-invested rest stops at a number of key road traffic routes.

Among them, the Satra bus stop invested by Phuong Trang in Tien Giang province is the largest in scale on the entire national traffic route. This bus stop has an area of ​​12 hectares, an investment capital of up to 100 billion VND, and a synchronous utility service system.

“We have carefully assessed the capacity profile of the Phuong Trang – Thanh Hiep Phat joint venture. This is one of the major investors, capable of leading the investment market in construction and operation of highway rest stops,” said a leader of the Vietnam Expressway Administration.

Many surprises ahead

In addition to the case of the Phuong Trang - Thanh Hiep Phat joint venture, another enterprise that is also expected to have great success in the bidding for investment projects to build rest stops on the Eastern North - South Expressway is the Vietnam National Petroleum Group ( Petrolimex ).

At the end of June 2024, the Petrolimex - Thua Thien Hue Petroleum Company consortium was selected as the investor of the Investment Project for construction and operation of the Km329+700 rest stop under the Mai Son - National Highway 45 Component Project with a value of 111 billion VND paid to the state budget; the preliminary value of the project implementation cost is 201,685 billion VND; the value of compensation, support and resettlement (M2) is 10,454 billion VND.

“With strong financial potential and the largest fuel supply station system in the country, it will not be surprising if Petrolimex continues to be named as the winning bidder for the rest stop projects being implemented by units under the Ministry of Transport,” said the leader of a business that submitted a bid for the Km329+700 Rest Stop Construction and Operation Project under the Mai Son – National Highway 45 Component Project.

According to Mr. Tran Chung, Chairman of the Vietnam Road Traffic Construction Investors Association, with nearly 50 rest stops on expressways needing investment in the next 2-5 years, this is a new business sector, attracting the attention of domestic and foreign investors.

However, this is a risky business field, where investors have to mobilize capital of up to 300 - 400 billion VND in a very short time (maximum 1.5 years), while the payback period lasts up to 25 years.

Because the public works system accounts for the majority of investment costs and costs a lot of operating costs, but provides free services, investors can only expect revenue from renting premises for food and beverage businesses, fuel businesses, etc.

The investment scale of rest stops is basically the same, so if the route has few vehicles or traffic growth is not as forecasted, the location of the rest stop is not really reasonable, customers spend little, etc., investors will certainly suffer losses.

Therefore, if rest stop investment is not considered as a field in the ecosystem (like the case of Phuong Trang Company) to be able to offset costs, the possibility of investors "going bankrupt" is very high.

The Phuong Trang - Thanh Hiep Phat joint venture has made careful calculations, as all three rest stops they won the bid for are adjacent to each other on the North - South expressway section in the East, about 300 km long, with very good traffic flow from Dau Giay (Dong Nai) - Phan Thiet (Binh Thuan) - Vinh Hao (Binh Thuan) - Cam Lam (Khanh Hoa).

Investing in a chain of 3 or more rest stops will help investors have more "room to perform" and reduce investment and operating costs when they have the same design and management system. It will be very risky if investors only operate 1 rest stop independently.

It should be added that, previously, the Ministry of Transport had received a proposal to establish a chain of modern multi-functional rest stops on the North-South Expressway from a joint venture between Vietnamese and Korean investors. This investor later withdrew the application and did not participate, because the management agencies organized bidding for each rest stop, instead of bidding in packages of 5 to 10 rest stops as they expected.

“The race to win the right to invest in the exploitation of rest stops on the North-South Expressway still promises many interesting surprises ahead, but is also full of pitfalls if investors are not alert enough to build a long-term, methodical business plan for this special field,” said Mr. Tran Chung.

Source: https://baodautu.vn/kinh-doanh-tram-dung-nghi-san-choi-moi-ken-nguoi-d218893.html


Comment (0)

No data
No data

Same tag

Same category

Young people go to the Northwest to check in during the most beautiful rice season of the year
In the season of 'hunting' for reed grass in Binh Lieu
In the middle of Can Gio mangrove forest
Quang Ngai fishermen pocket millions of dong every day after hitting the jackpot with shrimp

Same author

Heritage

Figure

Enterprise

Com lang Vong - the taste of autumn in Hanoi

News

Political System

Destination

Product