All night on Bien Hoa - Vung Tau highway through Dong Nai province

Báo Dân tríBáo Dân trí08/01/2025

(Dan Tri) - Under the bright lights of the construction site, hundreds of machines and workers worked diligently through the night to speed up the progress of the Bien Hoa - Vung Tau expressway through Dong Nai province.
Trắng đêm trên cao tốc Biên Hòa - Vũng Tàu qua tỉnh Đồng Nai - 1
In the first days of the year, the Bien Hoa - Vung Tau expressway construction site through Dong Nai province has become busier than ever. Contractors have increased manpower and machinery to speed up the project’s slow progress.
Trắng đêm trên cao tốc Biên Hòa - Vũng Tàu qua tỉnh Đồng Nai - 2
At component project 1, the section passing through Long Thanh district, after the site was handed over at the end of 2024, contractors deployed 3 shifts, 4 crews with a large amount of machinery and workers to make up for the delay.
Trắng đêm trên cao tốc Biên Hòa - Vũng Tàu qua tỉnh Đồng Nai - 3
A representative of Lizen Joint Stock Company said that the unit has maintained more than 100 machines and engineers and construction workers throughout the holidays, working 3 shifts, 4 shifts continuously day and night to speed up progress.
Trắng đêm trên cao tốc Biên Hòa - Vũng Tàu qua tỉnh Đồng Nai - 4
Engineer Ninh The Thuong shared: "The company has prepared equipment, materials, and workers in advance. After the locality handed over the site, we immediately started construction. It is expected that the unit will lay asphalt in January and complete 2.5km of the expressway before the April 30 holiday this year."
Trắng đêm trên cao tốc Biên Hòa - Vũng Tàu qua tỉnh Đồng Nai - 5
At the construction site, hundreds of machines from cranes, excavators... continuously work under bright lights.
Trắng đêm trên cao tốc Biên Hòa - Vũng Tàu qua tỉnh Đồng Nai - 6
"Dong Nai is entering the dry season, the weather is cool at night, the construction teams work very effectively. The company's leaders always care, support and encourage the brothers to focus on work to ensure the overall progress of the whole project," engineer Ninh The Thuong shared.
Trắng đêm trên cao tốc Biên Hòa - Vũng Tàu qua tỉnh Đồng Nai - 7
All machines are equipped with lighting systems for nighttime work. Construction units pay attention to labor safety.
Trắng đêm trên cao tốc Biên Hòa - Vũng Tàu qua tỉnh Đồng Nai - 8
Bien Hoa - Vung Tau Expressway section through An Phuoc Commune, Long Thanh District has completed leveling the ground, and is constructing a layer of crushed stone and hard concrete before paving the asphalt. This expressway section is expected to be completed by the middle of this year.
Trắng đêm trên cao tốc Biên Hòa - Vũng Tàu qua tỉnh Đồng Nai - 9
According to the implementation report of component project 1 of the Bien Hoa - Vung Tau expressway construction investment project, up to now, the cumulative output of the two construction packages has reached about 310 billion VND, equivalent to more than 12.4% of the total investment.
Trắng đêm trên cao tốc Biên Hòa - Vũng Tàu qua tỉnh Đồng Nai - 10
According to the Dong Nai Province Traffic Construction Project Management Board, the Bien Hoa - Vung Tau Expressway Component 1 project is 16km long through Dong Nai Province, starting from National Highway 1 (Bien Hoa City) and ending at Long An Commune (Long Thanh District) passing through Bien Hoa City and Long Thanh District. Component 1 has two construction packages, including Package 18 through Bien Hoa City, which is implementing 6 construction projects, including Buong River Bridge, roadbed, cross-drainage culvert, underpass, Super T beam casting and precast components, with current output reaching about 3.2%. Package 21 through Long Thanh District is organizing 15 construction projects, including Nuoc Trong Bridge, cross-over bridge, main route bridge, roadbed, weak soil treatment, and beam casting, with output reaching about 18.1%.
Trắng đêm trên cao tốc Biên Hòa - Vũng Tàu qua tỉnh Đồng Nai - 11
The Bien Hoa - Vung Tau Expressway project requires a total land area of ​​about 138 hectares, and has completed the handover of about 101.78 hectares, reaching 74% of the total required area. Package No. 21 is worth more than VND 1,400 billion and is constructed by a consortium (Lizen Joint Stock Company, Hai Dang Joint Stock Company, 368 Construction Joint Stock Company and Construction Corporation No. 1).
Trắng đêm trên cao tốc Biên Hòa - Vũng Tàu qua tỉnh Đồng Nai - 12
Bien Hoa - Vung Tau Expressway, passing through Dong Nai and Ba Ria - Vung Tau provinces, is nearly 54km long and was started in June 2023. In Dong Nai province, component project 1 and component project 2 will be constructed, while in Ba Ria - Vung Tau province, component project 3 will be constructed. In phase 1, the project will have a scale of 4 to 6 lanes (depending on each section). The total investment is more than 17,800 billion VND.

Comment (0)

No data
No data

Same tag

Same category

Re-enactment of the Ly Dynasty's Mid-Autumn Festival at Thang Long Imperial Citadel
Western tourists enjoy buying Mid-Autumn Festival toys on Hang Ma Street to give to their children and grandchildren.
Hang Ma Street is brilliant with Mid-Autumn colors, young people are excitedly checking in non-stop
Historical message: Vinh Nghiem Pagoda woodblocks - documentary heritage of humanity

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product