Implement key transport projects well to compensate for damage caused by storm No. 3

Báo Giao thôngBáo Giao thông17/09/2024


Efforts to complete transport infrastructure projects to demonstrate "national love and solidarity"

The meeting was held in person and online between the Government headquarters and the provinces and centrally-run cities that have important national projects and key works in the transport sector in the area.

The meeting aims to review and urge the work after the 13th meeting and discuss solutions, continue to remove difficulties and obstacles, and speed up the progress of works and projects.

Thủ tướng: Triển khai tốt các dự án giao thông trọng điểm để bù đắp thiệt hại do bão số 3- Ảnh 1.

Prime Minister Pham Minh Chinh delivers the opening speech at the 14th meeting of the State Steering Committee for key national projects and works in the transport sector (Photo: VGP/Nhat Bac).

In his opening speech, Prime Minister Pham Minh Chinh stated that, up to now, the list of projects monitored by the Steering Committee includes 40 major projects/92 component projects in 3 areas: Road, railway and aviation, passing through 48 provinces and centrally-run cities.

The Prime Minister emphasized that from now until the end of 2025, there are only about 15 months left, the workload is very large. Therefore, the Prime Minister suggested discussing solutions to speed up progress, ensure project quality; apply valuable experiences from the 500kV power line circuit 3 project.

Accordingly, it is necessary to create a vibrant emulation movement, mobilize forces, and create a combined strength with the entire political system participating under the leadership and direction of Party committees and authorities, and the active participation of the Fatherland Front and socio-political organizations.

Main contractors mobilize additional subcontractors to create jobs and livelihoods for people and businesses and improve the capacity of local contractors, with the spirit of "working together, winning together, enjoying together, and developing together".

The Prime Minister also took time to analyze the importance of strategic transport infrastructure.

"In particular, preliminary statistics show that super typhoon No. 3 caused about 40 trillion VND in damage. We must have solutions to compensate for these damages, including the task of promoting public investment disbursement and promoting three strategic breakthroughs, including a strategic breakthrough in transport infrastructure," said the Prime Minister.

Therefore, the implementation of key national transport infrastructure projects is an important political task, also demonstrating "national love and compatriotism". Ministries, branches, localities and enterprises must focus on doing it with the spirit and responsibility for the people and the country. Once said, it must be done, once committed, it must be implemented.

Many important tasks have been completed.

At the 13th meeting on August 8, the Prime Minister assigned 42 tasks to ministries, branches and localities, focusing on removing difficulties and obstacles, speeding up the progress of site clearance and providing construction materials, especially for key transport projects in the Southern region.

According to the report of the Ministry of Transport, up to now, the units have completed 11 tasks on time, are actively implementing 28 tasks of regular direction and management, one task that has not yet been due, and two tasks that have not yet been completed on time, of which a number of important tasks have been completed.

Thủ tướng: Triển khai tốt các dự án giao thông trọng điểm để bù đắp thiệt hại do bão số 3- Ảnh 2.

The meeting was held in person and online between the Government headquarters and the provinces and centrally-run cities that are hosting important national projects (Photo: VGP/Nhat Bac).

Regarding the implementation of construction and the movement "500 days and nights of competition to complete 3,000 km of expressway", the Ministry of Transport has coordinated with the localities assigned as the governing bodies to review the implementation plan, build detailed progress, especially the work of a "critical" nature to urge the units.

Most projects have sufficient material sources and favorable site clearance conditions, and construction progress meets requirements.

Some projects with great implementation value such as the North - South Expressway in the East phase 2021-2025, construction reached 52%, Chau Doc - Can Tho - Soc Trang section through An Giang reached 26%, Hanoi Ring Road 4 section through Hanoi reached 33%, Tuyen Quang - Ha Giang project section through Ha Giang reached 35%...

Some component projects are striving to be completed 3 to 6 months early.

However, the implementation of projects in some localities is still slow, such as Can Tho, Soc Trang at the Chau Doc - Can Tho - Soc Trang project, Bac Ninh at the Hanoi Ring Road 4 project, Cao Bang at the Dong Dang - Tra Linh project, Lang Son has just started construction of the Huu Nghi - Chi Lang project, especially at projects planned to be completed in 2025, including: Dong Nai at the Bien Hoa - Vung Tau component project 1 and the Ho Chi Minh City Ring Road 3 component project 3; Binh Duong at the Ho Chi Minh City Ring Road 3 project; Tuyen Quang at the Tuyen Quang - Ha Giang project.



Source: https://www.baogiaothong.vn/thu-tuong-trien-khai-tot-cac-du-an-giao-thong-trong-diem-de-bu-dap-thiet-hai-do-bao-so-3-192240917153840968.htm

Comment (0)

No data
No data

Same tag

Same category

Spend millions to learn flower arrangement, find bonding experiences during Mid-Autumn Festival
There is a hill of purple Sim flowers in the sky of Son La
Lost in cloud hunting in Ta Xua
The beauty of Ha Long Bay has been recognized as a heritage site by UNESCO three times.

Same author

Heritage

;

Figure

;

Enterprise

;

No videos available

News

;

Political System

;

Destination

;

Product

;