The joint venture contractor mobilized teams of highly skilled workers to roof the passenger terminal of Long Thanh airport. This is a very important item of the whole project.
According to engineers, the station roof has 5 layers, each layer must be constructed according to the correct technical process, with high precision. When installing the roof, it is carefully checked from flatness, tightness to weather resistance. "Each roof layer plays an important role such as insulation, waterproofing, protecting the surface to ensure durability... When installing a layer, it will be necessary to measure and align until it is correct before the new position can be covered", said Mr. Nguyen Van Tam, a roofing contractor.
Source: https://www.baogiaothong.vn/muc-so-thi-lop-5-lop-mai-nha-ga-hanh-khach-sieu-san-bay-long-thanh-19225010821380564.htm