Investors of 7 projects hope to soon resolve difficulties

Người Lao ĐộngNgười Lao Động21/02/2023


On the afternoon of February 20, Mr. Bui Xuan Cuong, Vice Chairman of the Ho Chi Minh City People's Committee, along with relevant departments and branches, had a direct meeting with investors of 7 projects facing difficulties in Ho Chi Minh City to listen and consider solutions.

Many years of problems and stagnation

The projects that the City People's Committee is considering to remove obstacles include: the commercial center and luxury apartment project on Ben Nghe Street (Tan Thuan Dong Ward, District 7); the Tan Thang sports and residential complex (Son Ky Ward, Tan Phu District); the Cuu Long apartment project (Ward 1, District 4); the Song Viet complex (Thu Thiem new urban area, Thu Duc City), the Thien Ly residential area (Phuoc Long B Ward, Thu Duc City), the 30.2-hectare project in Binh Khanh Ward (Thu Duc City) and the Co Giang apartment project (Co Giang Ward, District 1).

These projects mainly encounter problems related to apartment sale procedures, land tax calculation, construction permits, land price re-determination, inspection and examination, etc. Some projects have encountered problems and stagnation for many years and have not been resolved yet.

A typical example is the project of the commercial center and luxury apartments on Ben Nghe Street (Asiana Riverside, District 7) invested by Gotec Vietnam Co., Ltd. since 2018. The project has an area of ​​10,076.6 m2, including 2 blocks, 21 floors high with about 500 apartments; to date, the foundation, basement and first floor have been completed, the next floors are being built but have not been granted a license to open for sale. The reason is that the enterprise has submitted 3 applications to request a notice of housing eligibility for sale and lease-purchase for commercial housing, but the Department of Construction of Ho Chi Minh City has returned the application all the time with the reason of reviewing the transfer of land use purposes. Up to this point, the company's immediate losses have amounted to about 1,052 billion VND.

Song Viet Complex Project (Thu Duc City) is invested by Quoc Loc Phat Company (a member of Son Kim Land). The project has a scale of 4.8 hectares, stuck in the stage of granting confirmation of eligibility to sell and lease-purchase future housing for the project. The reason is due to the general planning of the new urban area of ​​Thu Thiem, not the fault of the investor.

The 30.2-hectare project in Binh Khanh Ward (Thu Duc City) invested by the 21st Century International Development Company Limited was later acquired by Novaland Group under the commercial name The Water Bay. The project is currently suspended for inspection and examination. In 2020, Novaland Group reported that it had invested up to VND 6,000 billion in the project but it was not implemented. Therefore, the company has repeatedly asked the Ministry of Construction to continue implementing this residential project.

The Co Giang apartment project (District 1) has been approved for investment by the Ho Chi Minh City People's Committee. Novaland Group is the project developer with the commercial name Grand Manhattan and has implemented construction up to the 28th floor but is stuck in the process of granting an investment certificate and enjoys incentives such as exemption from land use fees for the entire allocated land area. Because this is a project to renovate and rebuild old apartment buildings, the investor must compensate for the common use area.

Chủ đầu tư 7 dự án mong sớm tháo gỡ vướng mắc - Ảnh 1.

The Co Giang apartment project (Co Giang ward, District 1, Ho Chi Minh City) is facing difficulties in granting investment certificates and enjoying incentives such as exemption from land use fees. Photo: HOANG TRIEU

Keep waiting

The Tan Thang cultural, sports and residential complex project (Celadon City, Tan Phu district) has a scale of 82.5 hectares, approved by the Ho Chi Minh City People's Committee for Saigon Thuong Tin Tan Thang Real Estate Investment Joint Stock Company to be the investor. Afterwards, Gamuda Land Joint Stock Company acquired the majority of shares of Saigon Thuong Tin Tan Thang Real Estate Investment Joint Stock Company to own this project.

According to Gamuda Land, when buying back the shares, the old investor said that they would be exempted from taxes and they would only pay the recognized portion. However, the city later asked the new investor to pay more than 400 billion VND in taxes because the company did not directly pay compensation and resettlement support but only bought back the shares, so compensation and resettlement costs could not be deducted from land use fees and project land rent. Due to not agreeing to pay taxes, the project has been stalled for a long time, Gamuda Land was listed as owing more than 541 billion VND in taxes, including principal and interest.

Speaking to a reporter from Nguoi Lao Dong Newspaper right after the meeting, Mr. Nguyen Viet Anh, Chairman of the Board of Directors of Gotec Vietnam, commented that the meeting took place in a receptive spirit, and the city leaders and departments and branches listened to reports from businesses. "The city leaders have not immediately resolved the problems but promised to consider and respond soon. Although there is no way out, I really hope for good results, so that the project can continue to be implemented and products can be sold to the market, otherwise it will cause great damage to businesses" - Mr. Viet Anh expressed.

Novaland also said that the company hopes that after the meeting, the city leaders will listen and find ways to resolve difficulties so that the projects can be implemented, creating conditions for the company to overcome difficulties. The representative of Quoc Loc Phat Company also said that the meeting has not yet reached any conclusions and needs to wait for further opinions from the city leaders.

According to Mr. Le Hoang Chau, Chairman of the Ho Chi Minh City Real Estate Association, most of the problems of the projects at the meeting were difficult cases, so they lasted a long time and were difficult to solve. Therefore, the meeting only stopped at the level of listening and considering, then had a conclusion, and it was difficult to answer the enterprises immediately. Not to mention, there were problems under the central authority, so they had to be submitted for opinions.



Source: https://nld.com.vn/kinh-te/chu-dau-tu-7-du-an-mong-som-thao-go-vuong-mac-20230220220219004.htm

Comment (0)

No data
No data

Same tag

Same category

Spend millions to learn flower arrangement, find bonding experiences during Mid-Autumn Festival
There is a hill of purple Sim flowers in the sky of Son La
Lost in cloud hunting in Ta Xua
The beauty of Ha Long Bay has been recognized as a heritage site by UNESCO three times.

Same author

Heritage

;

Figure

;

Enterprise

;

No videos available

News

;

Political System

;

Destination

;

Product

;