Project "Promoting the value of Huynh Thuc Khang Memorial House" with construction items including: garden, road surface, bridge, toilet, garage, trees, electricity, water supply and drainage, value promotion area...
The project has a total adjusted investment of more than 49.1 billion VND, of which the People's Committee of Tien Phuoc district (old) has implemented more than 12.3 billion VND, the remaining 36.8 billion VND is continued by the Quang Nam Construction Investment Project Management Board.

According to the report, due to many reasons, the project's progress is slower than planned. The main reasons are compensation and site clearance; the impact on the power transformer station in the area...
After inspecting the areas with land clearance problems, Vice Chairman of the City People's Council Doan Ngoc Hung Anh requested the management boards to coordinate with relevant agencies to gradually resolve the difficulties and problems. Strive to complete the project before the 150th anniversary of Huynh Thuc Khang's birth (October 1, 2026).
Source: https://baodanang.vn/day-nhanh-tien-do-du-an-phat-huy-gia-tri-di-tich-nha-luu-niem-cu-huynh-thuc-khang-3305871.html
Comment (0)