The 'trillion-dollar' road expansion project in Quang Ninh is under construction at a standstill.

Việt NamViệt Nam14/12/2024


TPO – After more than 3 years of being approved, the National Highway 279 expansion project has only completed about 30% of the work volume and must be carried out at a slow pace due to problems in site clearance.

TPO – After more than 3 years of being approved, the National Highway 279 expansion project has only completed about 30% of the work volume and must be carried out at a slow pace due to problems in site clearance.

Overview of the project to upgrade and expand National Highway 279, 8.1 km long.

The 'trillion-dollar' road expansion project in Quang Ninh is under slow construction, photo 1

The project to renovate and upgrade National Highway 279 was approved by the People's Committee of Quang Ninh province in Decision No. 3568/QD-UBND dated December 6, 2022, invested by the Project Management Board (PMU) for investment in construction of agricultural and rural development works (NN&PTNT) of Quang Ninh province, to be implemented in the period of 2022-2025 with a total investment of more than VND 1,800 billion from the provincial budget.

The 'trillion-dollar' road expansion project in Quang Ninh is under slow construction, photo 2
The project is 8.1km long, starting at the intersection with National Highway 18, Quang Hanh Ward, Cam Pha City; ending at the Ha Long - Van Don Expressway Interchange (Dong La Interchange), Vu Oai Commune, Ha Long City.
The 'trillion-dollar' road expansion project in Quang Ninh is under slow construction, photo 3

However, up to now, the project has only completed nearly 30% of the total volume of items, construction sites are scattered along National Highway 279.

The 'trillion-dollar' road expansion project in Quang Ninh is under slow construction, photo 4The 'trillion-dollar' road expansion project in Quang Ninh is under slow construction, photo 5The 'trillion-dollar' road expansion project in Quang Ninh is under slow construction, photo 6

According to Tien Phong newspaper , at Quang Hanh intersection, Cam Pha city, the starting point of Highway 279 intersecting with Highway 18, the contractor has completed one span of the overpass. This is the intersection with Highway 18, with a large slope. Previously, this intersection often had cases of trucks losing control, causing traffic accidents.

The 'trillion-dollar' road expansion project in Quang Ninh is under slow construction, photo 7

At Dien Vong bridge area, the contractor has completed the construction of piers and piers, finished casting I33 girder and is preparing to install girder to cross the river. However, there is still no access road to the bridge at both ends of the bridge.

The 'trillion-dollar' road expansion project in Quang Ninh is under slow construction, photo 8

Along the 8.1 km long route, at some locations, slope reduction is being constructed and land compensation is being carried out at some locations.

The 'trillion-dollar' road expansion project in Quang Ninh is under slow construction, photo 9

Construction has been slow over the past time, putting the project at risk of falling behind schedule.

The 'trillion-dollar' road expansion project in Quang Ninh is under slow construction, photo 10The 'trillion-dollar' road expansion project in Quang Ninh is under slow construction, photo 11

A representative of the Project Management Board for Investment in Construction of Agricultural Works and Rural Development in Quang Ninh Province admitted that the project is under slow construction and is at risk of not being completed on time in 2025.

The 'trillion-dollar' road expansion project in Quang Ninh is under slow construction, photo 12

According to the investor, the reason is that the site clearance work has not been ensured according to plan, forcing the contractor to organize construction at a slow pace at the sites that have been handed over.

The 'trillion-dollar' road expansion project in Quang Ninh is under slow construction, photo 13

There are about 100 households and more than 20 organizations and businesses that are subject to site clearance, mainly located at Quang Hanh intersection, Cam Pha City. Because there is no site clearance plan and the site has not been handed over, contractors cannot mobilize machinery and equipment to work simultaneously on the route.

The 'trillion-dollar' road expansion project in Quang Ninh is under slow construction, photo 14
There are some locations that have flat ground but are in the middle of the elevation, making it impossible to construct the roadbed from the bottom up. Some locations cannot dump soil because the project follows the balanced excavation and embankment process.
The 'trillion-dollar' road expansion project in Quang Ninh is under slow construction, photo 15The 'trillion-dollar' road expansion project in Quang Ninh is under slow construction, photo 16

Currently, Ha Long City and Cam Pha City have just handed over the area managed by the State to the investor. After having the site, the investor requested the contractors to take advantage of the dry season to urgently mobilize machinery for construction.

The 'trillion-dollar' road expansion project in Quang Ninh is under slow construction, photo 17

Due to difficulties in construction site, contractors were forced to organize the casting of beams and components at a location nearly 5km away from the construction site.

The 'trillion-dollar' road expansion project in Quang Ninh is under slow construction, photo 18

The National Highway 279 expansion project has a total length of 8.1 km connecting Ha Long City and Cam Pha City of Quang Ninh Province. Photo: Google Maps.

Quoc Nam

Source: https://tienphong.vn/du-an-mo-rong-duong-nghin-ty-o-quang-ninh-thi-cong-cam-chung-post1700571.tpo


Comment (0)

No data
No data

Same tag

Same category

Spend millions to learn flower arrangement, find bonding experiences during Mid-Autumn Festival
There is a hill of purple Sim flowers in the sky of Son La
Lost in cloud hunting in Ta Xua
The beauty of Ha Long Bay has been recognized as a heritage site by UNESCO three times.