Giving gifts of gratitude to Mr. Nguyen Minh Luong's family.
Delegates performed the groundbreaking ceremony.
Ut Oi 3 and Ut Oi 4 Bridges were newly built with reinforced concrete structure, with a total estimated cost of over 1.3 billion VND, with Long Xuyen Ward People's Committee mobilizing Mr. Nguyen Minh Luong (commonly known as Ut Oi) to support the cost; People of Tan Phu and My Phu hamlets contributed more money, materials and labor days.
Of which, Ut Oi 3 Bridge is 6m long, 4m wide, construction cost is about 400 million VND; Ut Oi 4 Bridge is 15m long, 4m wide, construction cost is about 900 million VND; estimated construction time is about 60 days.
Two new bridges will replace the previous wooden and temporary iron bridges, ensuring convenient and safe travel for people.
News and photos: NGUYEN HUNG