Construction progress of pedestrian bridge on metro line 1 in Ho Chi Minh City

Báo Tiền PhongBáo Tiền Phong10/05/2024


TPO - Contractors are still working hard to speed up the construction of pedestrian bridges connecting the elevated stations of metro line 1 Ben Thanh - Suoi Tien. To date, two bridges have been completed, three bridges will be completed in May 2024.

Construction progress of pedestrian bridge of metro line 1 in Ho Chi Minh City photo 1

The Ho Chi Minh City Urban Railway Management Board said that it has completed the girder racking at 5/9 pedestrian bridges connecting to Metro Line 1. Of which, 2 pedestrian bridges at the High-Tech Park station and Binh Thai station have been completely completed.

Construction progress of pedestrian bridge of metro line 1 in Ho Chi Minh City photo 2
With the remaining 3 pedestrian bridges completed at Rach Chiec, Phuoc Long and Tan Cang stations, all items are expected to be completed in May 2024.
Construction progress of pedestrian bridge of metro line 1 in Ho Chi Minh City photo 3

For the 4 pedestrian bridges under construction at Thao Dien, An Phu, Thu Duc and National University stations, the investor is actively coordinating with contractors and consultants to develop a detailed plan to speed up the construction progress, striving to complete the project on time with the overall progress of the project, and put the project into operation in the fourth quarter of 2024.

Construction progress of pedestrian bridge on metro line 1 in Ho Chi Minh City photo 4

The HCM City Urban Railway Management Board added that the pedestrian bridges are designed with a unique U-beam structure, made up of two single beams (weight from 46 - 75 tons/beam), with a total length of each bridge from 80-150m, divided into spans and small segments from 30-35m.

Construction progress of pedestrian bridge on metro line 1 in Ho Chi Minh City photo 5

These pedestrian bridges not only facilitate people to connect to metro line 1 stations conveniently and safely, but also serve as the main escape route in case of emergency.

Construction progress of pedestrian bridge of metro line 1 in Ho Chi Minh City photo 6

Engineers and workers from the contractor and consulting joint venture are speeding up construction at the pedestrian bridges connecting metro line No. 1.

Construction progress of pedestrian bridge on metro line 1 in Ho Chi Minh City photo 7

In the coming time, the units agreed to add more human resources and construction teams at locations where the site has been handed over and construction permits have been granted.

Construction progress of pedestrian bridge on metro line 1 in Ho Chi Minh City photo 8
Construction progress of pedestrian bridge on metro line 1 in Ho Chi Minh City photo 9
Along with that, we need to strengthen the organization of day and night construction; shorten the leave days and holidays of engineers and contractor workers, and prioritize project work.
Construction progress of pedestrian bridge on metro line 1 in Ho Chi Minh City photo 10

The pedestrian bridge architecture is designed similar to the main station structure with a steel dome and heat-resistant roofing panels. Along both sides of the bridge are flower beds and trees, combined with natural ventilation, creating a comfortable feeling for passengers when approaching the station.

Construction progress of pedestrian bridge of metro line 1 in Ho Chi Minh City photo 11

Metro Line 1 has a total investment of more than 43,700 billion VND, nearly 20 km long from Ben Thanh (District 1) to Long Binh Depot (Thu Duc City), and has currently reached 98% of the workload.

Close-up of 2 super modern underground stations of Metro Line 1
Close-up of 2 super modern underground stations of Metro Line 1

Relocating and cutting down 185 trees to implement the connection project for metro line 1
Relocating and cutting down 185 trees to implement the connection project for metro line 1

Special guests of metro train No. 1 in Ho Chi Minh City
Special guests of metro train No. 1 in Ho Chi Minh City

Metro Line 2 investor explains why more than 400 trees had to be cut down
Metro Line 2 investor explains why more than 400 trees had to be cut down

Duy Anh



Source: https://tienphong.vn/tien-do-thi-cong-cau-bo-hanh-tuyen-metro-so-1-o-tphcm-post1635342.tpo

Comment (0)

No data
No data

Same tag

Same category

Spend millions to learn flower arrangement, find bonding experiences during Mid-Autumn Festival
There is a hill of purple Sim flowers in the sky of Son La
Lost in cloud hunting in Ta Xua
The beauty of Ha Long Bay has been recognized as a heritage site by UNESCO three times.

Same author

Heritage

;

Figure

;

Enterprise

;

No videos available

News

;

Political System

;

Destination

;

Product

;