Ia Ly commune needs to arrange forces to be on guard, monitor landslide developments, add warning signs, guide traffic flow and publicly announce the situation so that people and vehicles can proactively avoid risks.
The Department of Construction also requested the Ia Ly Hydropower Company to urgently report to the Vietnam Electricity Group to soon have a plan to fix the landslide section, ensuring safety and stable operation of the road.

In addition, the Department of Construction proposed that the Gia Lai Provincial People's Committee direct the Department of Agriculture and Environment to coordinate with relevant departments, branches and localities to inspect, assess the situation, count the damage to find solutions and support affected households in the landslide area.

Previously, SGGP Newspaper reported that the road leading to OPY 500kV Station - Ia Ly Hydropower Plant had completely collapsed with a length of 320m, 6m deep, paralyzing traffic and threatening 6 households. Currently, the collapsed location is showing signs of landslides spreading to neighboring locations.
Source: https://www.sggp.org.vn/vu-sut-lun-duong-vao-tram-500kv-o-gia-lai-phong-toa-vung-sat-lo-post818962.html
Comment (0)