Departments, branches, sectors and localities in the province have made great efforts in implementation, especially in completing investment procedures, site clearance, urging contractors to construct, making payments and disbursements. However, the progress of disbursement of public investment capital and national target programs of some agencies, units and localities is still low, not meeting requirements; many projects are behind schedule, the implementation volume and disbursement value are not commensurate with the time and capital plan assigned.
![]() |
Tam Son Ward is one of the units commended for its work in disbursing public investment capital in 2025. Photo: A corner of Tam Son ward. |
As of October 21, the whole province has disbursed 11,754,388 billion VND, reaching 57.6% of the plan. Of which, the disbursement of capital assigned during the year reached 10,839,704 billion VND, equal to 71.8% of the plan assigned by the Prime Minister .
The Chairman of the Provincial People's Committee highly appreciated and commended the agencies and units with positive results in the disbursement rate of public investment capital up to October 21, demonstrating a sense of responsibility and determination in direction and management. Specifically, for provincial-level units including the construction investment project management boards: Luong Tai (91.6%); Tan Yen (83.1%); Yen The (72.7%) and Bac Ninh Province Civil and Urban Development Board No. 1 (79.2%), Provincial Police (78.5%). For commune-level units including: Viet Yen (96.7%), Nhan Thang (96.7%), Dong Cuu (96.4%), Gia Binh (91.6%), Phu Khe (91.5%), Tam Son (90.4%).
At the same time, criticized units with low disbursement results include the Construction Investment Project Management Boards: Luc Ngan (11.9%); Gia Binh (18.1%); Chu (33.3%) and the Bac Ninh Province Traffic and Agriculture Project Management Board No. 1 (28.3%), Bac Ninh Province Civil Construction and Urban Development Management Board No. 2 (32.5%). Communes and wards include: Bien Dong (3.1%), Sa Ly (16.7%), An Lac (18.3%), Tien Phong (19.5%), Bao Dai (21.1%), Hap Linh (22.7%), Dong Phu (25.9%), Luc Nam (27%), Son Dong (28.1%), Hiep Hoa (28.9%). Units that have not reported disbursement results include: Thuan Thanh, Tam Tien, Nha Nam, Tien Du.
The Chairman of the Provincial People's Committee requested: Agencies, localities, project management boards, investors with low disbursement rates and no disbursement results reports must seriously review the collective and individual responsibilities involved, clarify the causes of slow disbursement, propose specific solutions and report the results to the Department of Finance before October 26 for synthesis and reporting to the Chairman of the Provincial People's Committee before October 28, 2025.
Assign the Department of Finance to synthesize and urge units and investors to speed up disbursement progress, report weekly (details of disbursed capital each week for each investor) propose commendation, criticism, report to the Provincial People's Committee, Chairman of the Provincial People's Committee as required: Party Committees, Party Secretaries of communes and wards strengthen leadership and direction of investment capital disbursement, speed up project progress, direct meetings, count weekly disbursement progress, identify this as an important political task in the last months of 2025 of the locality, ensure strict implementation of the directions of the Provincial Party Committee, People's Council, Provincial People's Committee on public investment capital disbursement in 2025.
Assign the Department of Home Affairs to synthesize and advise the Chairman of the Provincial People's Committee to consider disbursement results as one of the criteria for evaluating and classifying the level of task completion of heads of agencies, units, and localities in 2025.
Source: https://baobacninhtv.vn/bac-ninh-chu-tich-ubnd-tinh-phe-binh-cac-co-quan-don-vi-dia-phuong-co-ty-le-giai-ngan-von-dau-tu-cong-thap-postid429471.bbg