Difficult problem at Ho Chi Minh City Ring Road 4 Project

Việt NamViệt Nam04/09/2024


Arranging enough state capital to participate in the Ho Chi Minh City Ring Road 4 Project is a difficult problem when the central and local budgets cannot be allocated for the Project.

Route map of Ho Chi Minh City Ring Road 4.

Capital bottleneck

According to a recent report by the Ho Chi Minh City Department of Transport sent to the City People's Committee, because the total investment of the Ho Chi Minh City Ring Road 4 Project is up to 128,063 billion VND, during the process of researching the pre-feasibility report, localities encountered some difficulties, such as there is no mechanism for localities to use local budget capital to implement the Project, there is no mechanism to use local budget to support other localities to invest in bridges connecting two localities.

Besides the issue of mechanism, the biggest "bottleneck" in the Project that localities are concerned about is the large amount of state capital involved (over 50% of the total investment), while the local budget capital is facing difficulties, so it is difficult to balance for investment.

At the recent Southeast Regional Coordination Council Conference, Chairman of the Ho Chi Minh City People's Committee Phan Van Mai proposed that the Central Government support Binh Duong , Dong Nai and Ba Ria - Vung Tau provinces with 50% of the site clearance costs, estimated at about VND 10,000 billion, and request capital allocation in the 2021-2025 period, while Ho Chi Minh City will take care of it itself.

For Long An province alone, Mr. Mai proposed that the central budget support 75% of the total budget capital participating in the Project - about 28,400 billion VND. Of which, 6,700 billion VND will be allocated for site clearance in the 2021-2025 period, the remaining amount will be allocated in the 2026-2030 period.

Regarding the mechanism, the Chairman of the Ho Chi Minh City People's Committee proposed that a similar mechanism could be used to build Ring Road 4, with the central and local budgets being shared. However, there is currently no mechanism for one locality to use its budget to support another.

Bonds can be issued

Regarding the proposal of the Chairman of the Ho Chi Minh City People's Committee on capital allocation for the Ho Chi Minh City Ring Road 4 Project, Minister of Planning and Investment Nguyen Chi Dung said that the proposals of Ho Chi Minh City and localities are reasonable. However, the Minister said that the Central Capital Plan for the period 2026-2030 has not been approved by the National Assembly, so the capital source for the Project has not been determined. Therefore, it is possible to separate this project into a separate project, not included in the central budget use plan and can issue separate bonds for the Project, then the provinces borrow and later pay themselves.

From the perspective of the specialized ministry, Minister of Transport Nguyen Van Thang said that in case the central budget faces difficulties, there must be a breakthrough mechanism and policy to attract socialized resources. Transport infrastructure projects in the Southeast region have received great attention from investors, so there needs to be a flexible and diverse mechanism and policy to resolve capital problems.

Along with the solutions suggested by the ministries, a capital mobilization solution proposed by the localities is to allow the provinces where the Project passes through to locally adjust the general planning for the construction of functional areas and locally adjust the general urban planning approved by the Prime Minister (similar to Clause 2, Article 6, Resolution No. 98/2023/QH15 on piloting a number of specific mechanisms and policies for the development of Ho Chi Minh City). From there, localities can adjust the planning to auction land plots along the expressways, then take capital to reinvest in the Ring Road 4 Project.

According to the plan agreed upon by Ho Chi Minh City and localities, the City will take the lead in developing a specific policy mechanism applicable to Ring Road 4 construction projects to submit to competent authorities for appraisal in August 2024. After that, the Ministry of Planning and Investment, the Ministry of Transport and relevant ministries and branches will appraise and report to the Prime Minister in September to submit to the National Assembly for approval at the session at the end of 2024.

Source: https://baodautu.vn/bai-toan-kho-tai-du-an-duong-vanh-dai-4-tphcm-d223669.html


Comment (0)

No data
No data

Same tag

Same category

Visit Lo Dieu fishing village in Gia Lai to see fishermen 'drawing' clover on the sea
Locksmith turns beer cans into vibrant Mid-Autumn lanterns
Spend millions to learn flower arrangement, find bonding experiences during Mid-Autumn Festival
There is a hill of purple Sim flowers in the sky of Son La

Same author

Heritage

;

Figure

;

Enterprise

;

No videos available

News

;

Political System

;

Destination

;

Product

;