[Photo] Binh Trieu 1 Bridge has been completed, raised by 1.1m, and will open to traffic at the end of November.

After a month of construction, the 11,000-ton Binh Trieu 1 bridge has been raised more than 1 meter. By the end of November 2025, the project will be fixed and the remaining items will be completed to open to traffic soon, reducing congestion at the eastern gateway of Ho Chi Minh City.

Báo Nhân dânBáo Nhân dân02/10/2025

ndo_br_2.jpg
After more than a month of urgent construction, on September 30, Binh Trieu 1 Bridge in Ho Chi Minh City - the vital route across the Saigon River - completed the clearance raising phase.
ndo_br_3.jpg
After one month of construction, the 11,000-ton Binh Trieu 1 Bridge in Ho Chi Minh City has been raised by 1.1m.
ndo_br_4.jpg
This is considered an important milestone, opening the final phase including structural reinforcement, road surface completion, and preparation for reopening to traffic.
ndo_br_5.jpg
According to the reporter's record on October 2, after more than a month of construction, the Binh Trieu 1 bridge span has been raised by 1.1m, reaching a clearance height of 7m. This is an important parameter, meeting the technical requirements, and at the same time creating the premise for the next items to be deployed smoothly, ensuring the progress of traffic opening according to plan.
ndo_br_6.jpg
At the scene, the bridge span had completely separated from the abutment, creating a clear gap.
ndo_br_7.jpg
This shows that the entire static lifting process is carried out very elaborately, requiring absolute technical precision.
ndo_br_8.jpg
To do this, the construction unit used a hydraulic jack system combined with hundreds of steel wedge plates, meticulously operating to ensure balance for the giant structure weighing thousands of tons.
ndo_br_9.jpg
The entire bridge structure is gradually raised, ensuring safety and stability throughout the construction process.
ndo_br_10.jpg
Under the bridge, hundreds of steel plates support the massive structure.
ndo_br_11.jpg
During the construction process, the team of engineers and workers are on duty 24/7 at the bridge piers, taking turns operating the jacking and additional wedge systems. Every detail is strictly monitored to ensure absolute safety for the project as well as the proposed progress.
ndo_br_12.jpg
According to the Road Traffic Infrastructure Management Center, Ho Chi Minh City Department of Construction, the work of raising the clearance of Binh Trieu 1 Bridge has been completed as planned. Currently, the contractor has entered the stage of inspection, steel reinforcement, and bridge piers reinforcement. It is expected that by November 30, the bridge will be completed and the surface will be returned to traffic.
ndo_br_13.jpg
The two projects to raise the clearance of Binh Trieu 1 Bridge and Binh Phuoc 1 Bridge are expected to create conditions for cargo and tourist boats to travel on the Saigon River more safely and smoothly. Along with that, the Ho Chi Minh City Department of Construction will coordinate with functional units to review and evaluate the entire bridge system with unsynchronized clearance to develop an implementation plan in the next phase.

Source: https://nhandan.vn/anh-cau-binh-trieu-1-da-hoan-tat-nang-cao-them-11m-cuoi-thang-11-thong-xe-post912472.html


Comment (0)

No data
No data

Same tag

Same category

Visit Lo Dieu fishing village in Gia Lai to see fishermen 'drawing' clover on the sea
Locksmith turns beer cans into vibrant Mid-Autumn lanterns
Spend millions to learn flower arrangement, find bonding experiences during Mid-Autumn Festival
There is a hill of purple Sim flowers in the sky of Son La

Same author

Heritage

;

Figure

;

Enterprise

;

No videos available

News

;

Political System

;

Destination

;

Product

;