Chairman of Lam Dong Provincial People's Committee Ho Van Muoi has just signed a document requesting departments, branches and localities to urgently focus on speeding up the disbursement of public investment capital in 2025.
According to the document, recently, the Provincial People's Committee has directed very strongly but the disbursement of public investment capital in 2025 still has not had positive changes (by September 30, 2025, only about 27% of the capital plan was disbursed).
Therefore, to accelerate the disbursement of public investment capital in 2025 in the last months of the year, the Provincial People's Committee requested the Department of Finance to preside over and coordinate with relevant units to advise the Provincial People's Committee on a document to severely criticize investors who disbursed capital by September 30, 2025 below the province's average level; draft a document reporting to the Provincial Party Standing Committee and the Provincial Party Standing Committee on the province's capital disbursement situation, the implementation of public investment capital disbursement tasks of units and investors, causes and solutions in the coming time. Complete and report to the Provincial People's Committee before October 5.
Every Thursday, report to the Provincial People's Committee on the disbursement results of each investor, difficulties and problems; propose directions to competent authorities to handle each group of problems, ensuring 6 clarity: Clear people, clear work, clear responsibility, clear authority, clear time, clear results.
Adjust the medium-term public investment plan for the period 2021 - 2025 and 2025; in which, review and adjust capital to projects with good progress and high disbursement capacity, review debt payment projects (including debt payment projects without a medium-term list of needs) to increase the arrangement of debt payment capital.

In particular, synthesize and advise the Provincial People's Committee to approve the disbursement plan for each week and month of projects with capital plans arranged for 2025 (including the capital plan for 2024 extended to 2025) from 30 billion VND or more; report to the Provincial People's Committee before October 10.
The Provincial People's Committee also requested provincial project management boards and investors to be resolute, focus on work, urge, speed up progress, develop detailed implementation plans for each project, and ensure time savings for each step and stage in the implementation process.
Resolutely and promptly handle contractors who violate progress, delay in payment procedures for completed volume, and violate signed contracts as prescribed; if necessary, terminate the contract and immediately replace other capable contractors. In addition, contract advances, contract guarantees, and advance recovery must be strict, ensuring compliance with legal regulations, absolutely preventing loss or ineffective use of the state budget.
Departments, branches, sectors, People's Committees of communes, wards and special zones, according to their functions, tasks and management areas, closely coordinate with investors, regularly inspect and urge the implementation of work at the agencies and localities under their management related to the implementation and disbursement of public investment capital.
Request the Chairmen of the People's Committees of communes, wards and special zones to directly participate in dialogue with the people, mobilize the entire political system to join in. Resolutely handle and enforce cases of taking advantage of state policies for personal gain, cases of procrastination, intentional violations, affecting the progress of project investment, socio-economic development of the locality, etc.
Source: https://baolamdong.vn/chu-tich-ubnd-tinh-lam-dong-chi-dao-phe-binh-nghiem-khac-chu-dau-tu-giai-ngan-von-dau-tu-cong-duoi-muc-trung-binh-394601.html