![]() |
Deputy Secretary of the Provincial Party Committee, Chairman of the People's Committee of Dong Nai province Vo Tan Duc chaired the regular meeting on the progress of public investment disbursement in 2025. Photo: Pham Tung |
According to Chairman of the Provincial People's Committee Vo Tan Duc, by 2025, Dong Nai province has set a target of double-digit economic growth. To achieve this target, one of the priority solutions is to complete the disbursement of 100% of the public investment plan. However, as of the end of September, the province's public investment disbursement rate has not yet met the progress requirements.
Assessing the causes, Chairman of the Provincial People's Committee Vo Tan Duc said: The main causes are site clearance; coordination between agencies and units in implementing tasks as well as the capacity of construction contractors. In particular, problems with site clearance are still the biggest "bottleneck" affecting the progress of public investment disbursement.
![]() |
Deputy Secretary of the Provincial Party Committee, Chairman of the People's Committee of Dong Nai province Vo Tan Duc delivered a concluding speech at the conference. Photo: Pham Tung |
Emphasizing that there is not much time left in 2025, while the remaining capital that needs to be disbursed is very large, Chairman of the Provincial People's Committee Vo Tan Duc requested units and investors, especially those assigned large capital sources, to focus on "working day and night" to complete the disbursement as committed.
The Department of Finance reviews and updates the capital plan and progress of each project, and reports to the Provincial People's Committee on the disbursement results of each investor unit every Thursday. In particular, it clearly states the units with disbursement rates lower than the national average. For these units, the heads must be responsible to the Provincial People's Committee.
Along with that, before October 15, the investor units must send the Department of Finance a summary of the detailed capital disbursement critical path for each project, clearly stating the difficulties and solutions to compensate for the capital disbursement progress. The Provincial People's Committee Office is responsible for monitoring the implementation progress according to the critical path that the units have committed to.
The Department of Agriculture and Environment coordinates with localities to resolve difficulties and obstacles in site clearance. Heads of communes and wards must be responsible for site clearance for projects passing through their areas. The Department of Home Affairs coordinates with the Department of Finance to propose a mechanism to evaluate and handle heads of units that are slow to disburse public investment capital.
In particular, investors must strictly handle and terminate contracts with contractors who construct projects that do not ensure progress.
![]() |
Representative of Project Management Board of Region 5 speaking at the conference. Photo: Pham Tung |
According to the Department of Finance, in 2025, the public investment capital plan in the province has been allocated more than 25.6 trillion VND. As of the end of September 2025, the total public investment capital has been disbursed nearly 13 trillion VND, reaching 40.5% of the plan assigned by the Prime Minister. If not counting the capital plan of more than 8 trillion VND of the Gia Nghia - Chon Thanh Expressway Project and the newly assigned additional 1.2 trillion VND, the province's capital disbursement rate reaches 57% of the plan.
Pham Tung
Source: https://baodongnai.com.vn/kinh-te/202510/phai-xem-hoan-thanh-nhiem-vu-giai-ngan-von-dau-tu-cong-la-danh-du-va-trach-nhiem-c5a4cd7/
Comment (0)