Vietnam.vn - Nền tảng quảng bá Việt Nam

T&T GROUP COMPLETED THE SAVAN 1 WIND POWER TRANSMISSION LINE TO VIETNAM

Right before the 80th National Day Celebration on September 2, the 220kV transmission line from the Savan 1 wind power plant in Laos was completed after more than 6 months of rapid construction; ready to be connected to Vietnam's national power grid in the near future.

Việt NamViệt Nam31/08/2025

This is an important milestone, demonstrating the determination of the staff and workers of Savan 1 Wind Power Company Limited (a member company of T&T Group) and the contractor; thereby continuing to realize T&T Group's "cross-border" energy investment strategy, contributing to increasing the national electricity supply, while promoting the strong economic cooperation between Vietnam and Laos.

After more than 6 months of rapid construction, the 220kV transmission line from the Savan 1 wind power plant in Laos has been completed and is ready to be connected to Vietnam's national power grid in the near future.

Overcoming the sun and rain to complete the special transmission line

Previously, on January 9, 2025, within the framework of the Vietnam - Laos Investment Cooperation Conference, witnessed by Prime Minister Pham Minh Chinh and Lao Prime Minister Sonexay Siphandone, the Lao Ministry of Planning and Investment , on behalf of the Government of the Lao People's Democratic Republic, awarded the concession contract for the Savan 1 wind power project to Savan 1 Wind Power Company Limited (a member unit of T&T Group).

Under the contract, the Government of the Lao People's Democratic Republic agreed to allow Savan 1 Wind Power Company Limited to design, construct, own and operate the Savan 1 wind power project with a contract term of up to 25 years to export and sell electricity to Vietnam. The project is deployed in Savannakhet province with a total installed capacity of up to 495 MW, a total investment of about 768 million USD. According to the plan, phase 1 of the project has an installed capacity of 300 MW, a total investment of more than 490 million USD and will be put into commercial operation by the end of 2025.

Leaders of the Lao Ministry of Planning and Investment awarded the concession contract for the Savan 1 wind power project to Mr. Nguyen Thai Ha, General Director of Savan 1 Wind Power Company Limited (second from left). (Photo: Nhat Bac/VGP)

At this time, the most important task is to soon build a 220kV transmission line connecting the Savan 1 wind power plant with the tower in Vietnam. This is considered the key "bloodline" to bring clean electricity from the Land of a Million Elephants to the Fatherland according to the proposed plan.

Mr. Nguyen Thai Ha, General Director of Savan 1 Wind Power Company Limited, said that in terms of scale, the transmission line has a total length of 52.56 km, running on the territory of Laos. The starting point of the line is located at G7, next to the border of the two countries. The end point connects to the 220kV transformer station of Savan 1 Wind Power Plant.

“The entire line includes 117 pole positions and 30 anchorages. The poles are designed as galvanized steel towers connected by bolts; the reinforced concrete foundation is cast in place,” added the General Director of Savan 1 Wind Power Company.

Realizing the importance of this special “bloodline”, right from the beginning, the leaders of T&T Group requested Savan 1 Wind Power Company and the General Contractor IPC E&C to coordinate closely and promptly carry out the first tasks. In fact, just 1 day after the Concession Contract was signed, hundreds of officers and workers began the process of clearing, cleaning the site, and making access roads to the key positions in the design.

Recalling the early days, General Director Nguyen Thai Ha said: The implementation of the project faced many challenges. First, because the construction was carried out in a neighboring country, all materials and equipment had to be brought from Vietnam. The company and the contractor had to complete many import and export procedures and apply for permits to be able to put human resources and machinery in position. In addition, the complex terrain, passing through many hills, mountains, villages, etc. also made the construction process difficult; not to mention the objective impacts from the weather.

Actual project image December 2024.

“The Group's leaders have directed the Company to create maximum conditions for the General Contractor to quickly access the site, gather supplies, materials, and human resources; and support related procedures so that the contractor can have the best working conditions,” Mr. Ha recalled.

Thanks to this overall effort, exactly 1 month later, on February 10, the foundation system was deployed. By mid-March, nearly 500 cadres and workers had erected poles on the field. The spirit of high determination, overcoming the sun and rain, was maintained continuously on the entire 2 circuits of the great project; thereby creating a rare miracle in the speed of deployment. By May 15, meaning only 3 months later, the first meters of wire were pulled up to the high points. Hundreds of people, carrying the dream of connecting the national power line, did not mind the sun or rain to connect the vital transmission line.

Then, on the evening of August 31, joy burst out when the contractor successfully pulled the power line across the legendary Sepon River, the natural border between Vietnam and Laos; completing the connection of the transmission line from Savan 1 to the first pole of the 220kV line on the Vietnamese side. The power transmission line has now "touched the gateway" to the motherland, carrying with it the pride of the solidarity and determination of the workers to overcome difficulties, while also containing the aspiration to "reach high and fly far" in the journey of building and developing the country.

After more than 6 months of rapid construction, the 220kV transmission line from the Savan 1 wind power plant in Laos has been completed.

“When looking at the cable line stretched across the Sepon River, the entire construction team was extremely moved. After more than 200 days of hard work, the 'line' connecting the two banks has finally taken shape,” a worker from the General Contractor shared.

Unable to hide her joy, Ms. Nguyen Thi Thanh Binh, Deputy General Director of T&T Group, Chairman of T&T Energy, affirmed that the event is an important milestone in the formation of the entire transmission line connecting Savan 1 wind power plant to the 220kV Lao Bao transformer station, ensuring the plant's on-time energization (COD) before December 31, 2025.

This result was achieved thanks to the close direction of the Group's leaders and Savan 1 Wind Power Company Limited. Hundreds of officers and employees of the Company and the General Contractor did not mind the difficulties, hardships, and poor living conditions, working in the mountainous border area, racing against time to complete in the shortest time. The event was even more meaningful as it took place right before the 80th National Day Celebration on September 2; thereby, affirming the capacity and determination of T&T Group in making competitive achievements, practically celebrating the country's major holidays", emphasized the Deputy General Director of T&T Group.

Continuing to realize T&T Group's cross-border energy strategy

In fact, the completion of the transmission line construction in Laos is a testament to the commitment to “tell the truth, do the truth”; and is also an important step forward in T&T Group’s “cross-border” energy investment strategy.

According to Ms. Nguyen Thi Thanh Binh, Deputy General Director of T&T Group, the investment in Savan 1 Wind Power Plant and the connection with the national transmission grid are of great significance, contributing to increasing the power supply for the national power system, gradually realizing the cooperation commitment between Vietnam and Laos as well as in line with the electricity import orientation in the National Power Development Plan approved by the Prime Minister in Decision No. 500/QD-TTg dated May 15, 2023. Savan 1 Wind Power Plant is also the largest onshore wind power project that T&T Group has invested in to date.

Ms. Nguyen Thi Thanh Binh, Deputy General Director of T&T Group (left) affirmed that the investment in Savan 1 Wind Power Plant and its connection with the national transmission grid is of great significance.

T&T Group's journey is not only a story of investment in energy, but also a testament to the aspiration of a private enterprise in the process of accompanying the country in developing sustainable energy. T&T Group aims to reach a total power generation capacity of 16,000 - 20,000 MW by 2035, accounting for about 10% of Vietnam's power system capacity, most of which is from clean energy sources such as solar power, wind power, LNG power, biomass power and green hydrogen/ammonia, aiming towards the common goal of bringing Vietnam to net zero emissions by 2050.

Up to now, the corporation of businessman Do Quang Hien has deployed a cumulative investment of a total capacity of 2,800 MW; of which 10 wind and solar power plants have been completed and put into operation in many provinces and cities across the country, with a total installed capacity and connection to the national grid reaching nearly 1,000 MW.

T&T Group's journey is not only a story of investment in energy, but also a testament to the aspiration of a private enterprise in the process of accompanying the country in developing sustainable energy.

In addition, T&T Group is also in a joint venture with KOGAS, KOSPO, HANWHA (Korea) to implement the Hai Lang LNG power project Phase 1 with a capacity of 1,500 MW, investment capital of about 2.5 billion USD, expected to operate in 2029. Not stopping there, T&T Group is continuing to develop and invest in many renewable energy projects, low carbon emission projects. Typical projects include solar power, onshore and offshore wind power, biomass power, LNG power, converting raw materials from coal-fired thermal power plants to LNG, battery energy storage system (BESS) manufacturing plants, researching new types of energy such as hydrogen, ammonia, etc.

The projects aim to supply electricity to the national grid, sell electricity to FDI enterprises under the direct power purchase agreement (DPPA), provide energy storage solutions for renewable energy plants, provide green electricity to produce green hydrogen, many projects have been approved in the Plan to implement the Power Plan VIII and are continuing to be added to the adjusted Power Plan VIII. T&T Group is preparing the necessary conditions to deploy investment in construction and put the projects into operation in the period 2026-2030.

To implement the projects, Mr. Hien's group has cooperated with many of the world's leading partners in the energy sector such as: Hanwha, Kogas, Kospo, SK E&S (Korea); erex, Marubeni, Sojittz, JPower (Japan); Cospower, Gedi, Goldwind (China), BP (UK), Vinacom (Laos)... In particular, Standard Charted Bank has committed a 6 billion USD funding package for T&T Group's green energy projects.

Back to the T&T people in Savannakhet. In the historic days of September, the officers and employees of Savan 1 Wind Power Company Limited and the General Contractor stood on this side of the Sepon River looking towards the motherland Vietnam. After many months of eating in the forest and sleeping in the mountains, finally, the vital power line from the neighboring land was successfully connected to the Fatherland. By the legendary river, everyone was excitedly looking forward to a bright future, where clean electricity from the Land of a Million Elephants will be integrated into the national grid. And Sepon, the natural border between Laos and Vietnam, in a moment turned into a river of light, of faith and hope...

Source: https://www.ttgroup.com.vn/tt-group-hoan-thanh-duong-day-truyen-tai-dien-gio-savan-1-ve-viet-nam


Comment (0)

No data
No data

Same category

Visit U Minh Ha to experience green tourism in Muoi Ngot and Song Trem
Vietnam team promoted to FIFA rank after victory over Nepal, Indonesia in danger
71 years after liberation, Hanoi retains its heritage beauty in the modern flow
71st anniversary of Capital Liberation Day - stirring up the spirit for Hanoi to step firmly into the new era

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product