Up to now, the volume of items has reached 95%, in which, block 1 and block 2 have completed construction, are installing electrical systems; the hall, canteen, dormitory are installing furniture...
To ensure progress and quality, the contractor has mobilized maximum resources, engineers, and workers to divide into many construction teams to complete the project items and complete by the end of this month.

The new construction project of Lao Cai Specialized High School is one of the key projects to celebrate the province's major holidays in 2025. The project's investment and construction affirms the province's interest in education , especially high-quality education, to train human resources for the locality. According to the plan, the project will be completed and put into use in the 2025-2026 school year.
The project to build a new Lao Cai Specialized High School was approved by the People's Committee of Lao Cai province to be implemented in the period of 2021 - 2025, with a total investment of 350 billion VND, starting in February 2024.
Source: https://baolaocai.vn/ban-giao-cac-khoi-nha-hoc-nha-hieu-bo-truong-thpt-chuyen-lao-cai-truoc-ngay-157-post648068.html