The Government has decided to implement the Ho Chi Minh City Ring Road 4 Construction Investment Project (the Project) which was decided by the National Assembly in Resolution No. 220/2025/QH15 to ensure compliance with legal regulations, progress, construction quality, strict management and economical, effective, public and transparent use of capital. Specifically:
The Chairman of the People's Committee of Ho Chi Minh City and the Chairmen of the People's Committees of Dong Nai and Tay Ninh provinces exercise the authority of the investment decision maker, organize the preparation and appraisal of the feasibility study report and decide to approve the project.
The order, procedures, authority to appraise and decide on investment in component projects are implemented similarly to those for group A projects according to the provisions of law on public investment.
The People's Committee of Ho Chi Minh City and the People's Committees of Dong Nai and Tay Ninh provinces organize the appraisal and approval of component projects according to the provisions of the Investment Law under the public-private partnership method.
The management and use of state budget capital to support the construction of works and infrastructure systems arranged from public investment capital sources in component projects implemented under the public-private partnership method shall be carried out in accordance with the provisions of Clause 5, Article 70 of the Law on Investment under the public-private partnership method.
The Resolution clearly states that the Chairman of the People's Committee of Ho Chi Minh City and the Chairmen of the People's Committees of Dong Nai and Tay Ninh provinces and the heads of competent agencies shall apply the form of designated bidding in the process of implementing the Project for consulting, non-consulting, consulting packages for planning adjustment and construction of infrastructure for resettlement areas. The order and procedures for implementing designated bidding shall comply with the provisions of the law on bidding.
The Resolution allows the People's Committee of Ho Chi Minh City and the People's Committees of Dong Nai and Tay Ninh provinces to simultaneously carry out a number of tasks related to land recovery, compensation, support, resettlement and identification of construction solid waste dumping sites during the project preparation phase.
The Resolution also allows simultaneous implementation of procedures to shorten the time for performing the following tasks: appraisal and decision to approve the appraisal results of environmental impact assessment reports; local adjustment of planning related to the Project to ensure the progress of implementing component projects; the above procedures must ensure the principle that the results of some tasks performed in the previous step are the basis for implementing the following tasks according to the provisions of law on construction investment.
The Resolution also assigns specific tasks to a number of ministries and branches for implementation. The Ho Chi Minh City People's Committee performs the task of the focal agency organizing the implementation of the Project, is responsible for being the focal agency organizing the implementation of the Project, ensuring the consistency and overallity of the entire Project; presides over the synthesis, submits to competent authorities for consideration and decision on adjusting the Project investment policy in case of arising factors leading to the need to adjust the Project investment policy.
The People's Committee of Ho Chi Minh City shall preside over the preparation of reports and submissions of the Government to the Ministry of Construction for synthesis and submission to competent authorities on the implementation status of the Project according to regulations and preside over and coordinate with localities to organize the development of progress and detailed plans for the implementation of the Project; develop a coordination mechanism between relevant ministries, branches and localities to implement component projects to ensure progress, quality, efficiency and synchronization; preside over the synthesis and coordination with the People's Committees of Dong Nai and Tay Ninh provinces to carry out investment supervision and evaluation according to the provisions of law.
Based on the specific situation and conditions, the People's Committee of Ho Chi Minh City will preside over the establishment of a Working Group to implement the Project immediately after this resolution of the Government is issued.
The Government assigned the People's Committee of Ho Chi Minh City and the People's Committee of Dong Nai province to report to the People's Council of the same level to decide to adjust to the form of public investment in case the component project with the People's Committee of Ho Chi Minh City and the People's Committee of Dong Nai province as the competent authority cannot select an investor.
The People's Committee of Ho Chi Minh City and the People's Committees of Dong Nai and Tay Ninh provinces are fully responsible for the progress, quality and efficiency of the projects under their management; absolutely do not allow any negativity or waste that causes loss of state assets. At the same time, exercise the authority and responsibility of the investment decision maker and competent authority according to current regulations in organizing the implementation of the projects, striving to complete the project in 2028 and put it into operation in 2029.
Source: https://www.sggp.org.vn/chinh-phu-ban-hanh-nghi-quyet-phan-dau-dua-duong-vanh-dai-4-tphcm-vao-khai-thac-nam-2029-post814905.html