Many solutions to speed up the progress of Can Tho Expressway

Việt NamViệt Nam24/09/2024


The North-South Eastern Expressway Project, phase 2021-2025, Can Tho - Ca Mau section (Can Tho - Ca Mau Expressway) has a length of more than 110km, with a total investment of more than VND 27,500 billion.

The project is divided into two sub-projects. Of which, the Can Tho – Hau Giang section is more than 37km long, with an investment of more than VND 10,370 billion; the Hau Giang – Ca Mau section is more than 73km long, with an investment of more than VND 17,152 billion.

Nhiều giải pháp thúc tiến độ cao tốc Cần Thơ - Cà Mau- Ảnh 1.

Can Tho - Ca Mau Expressway has reached 42% progress.

According to the report of My Thuan Project Management Board (investor), as of September 21, the project's construction output reached 42%, 15% behind schedule.

Of which, more than 91km of the main route has been treated for weak soil by loading method; 28 bridges have been completed, and the remaining 89 bridges are expected to be completed by the end of 2024.

To speed up the project, from the beginning of September 2024, the investor and contractors signed a commitment to mobilize finance, equipment, and materials to implement the construction. In which, the focus is on mobilizing sand resources to reach 70% of the demand.

Mr. Tran Van Thi, Director of My Thuan Project Management Board, said that the prerequisite for completing the project in 2025 is to complete the sand loading work.

After a period of effort, the sand source for the project has been basically resolved. Contractors will try to exploit all river and sea sand sources. From there, focus on filling the remaining section in 2024.

To ensure the goal of completing the project by the end of 2025, the Director of My Thuan Project Management Board said that he has asked contractors to re-establish detailed construction plans for the remaining items of the project in a scientific manner, ensuring that the delayed progress can be made up.

At the same time, prioritize financial resources, mobilize equipment, machinery, and construction labor in "3 shifts, 4 shifts", work during holidays and Tet, regularly check and supervise to ensure progress, quality, and technique.

In addition, arrange adequate internal personnel to coordinate with the investor to carry out acceptance and payment work, to avoid financial shortages at the construction site.

In addition, the Board also requested the supervision consultant to inspect, review the operation and urge the contractor to mobilize equipment and materials according to the committed schedule. There is a timely report and advice on solutions to handle any delay in implementation by the contractor.

Source: https://www.baogiaothong.vn/nhieu-giai-phap-thuc-tien-do-cao-toc-can-tho-ca-mau-19224092418054916.htm


Comment (0)

No data
No data

Same tag

Same category

Spend millions to learn flower arrangement, find bonding experiences during Mid-Autumn Festival
There is a hill of purple Sim flowers in the sky of Son La
Lost in cloud hunting in Ta Xua
The beauty of Ha Long Bay has been recognized as a heritage site by UNESCO three times.

Same author

Heritage

;

Figure

;

Enterprise

;

No videos available

News

;

Political System

;

Destination

;

Product

;