On the morning of October 17, the Provincial People's Committee held a thematic conference on basic construction in September 2025 in both in-person and online formats. Provincial Party Committee member and Vice Chairman of the Provincial People's Committee Truong Cong Thai chaired the meeting.

Báo Đắk LắkBáo Đắk Lắk17/10/2025

According to the report of the Department of Finance, the total public investment plan for 2024 extended to 2025 managed by the province is 2,320.7 billion VND; by September 30, 1,034.5 billion VND had been disbursed, reaching 44.6%.

Regarding the public investment plan for 2025, the total capital allocated is 15,640.88 billion VND. Of which, the capital for project implementation is 13,804.88 billion VND; by October 15, 13,092.67 billion VND has been allocated in detail to each project category, reaching 94.8%. The remaining 712.2 billion VND has not been allocated in detail. Currently, the Department of Finance is reviewing, advising on adjustments and allocation to eligible projects to speed up disbursement progress.

Provincial Party Committee member, Vice Chairman of the Provincial People's Committee Truong Cong Thai chaired the meeting.
Vice Chairman of the Provincial People's Committee Truong Cong Thai highly appreciated the efforts of units and localities in performing the task of disbursing public investment capital.

Regarding the disbursement of the 2025 public investment plan, by October 15, 5,583.24 billion VND had been disbursed, reaching 42.6% of the plan, an increase of 146.18 billion VND compared to September 30. Specifically, the central budget disbursed 2,942.59 billion VND, reaching 35.8% of the plan, an increase of over 136 billion VND; the local budget disbursed 2,640.6 billion VND, reaching over 54% of the plan, an increase of over 10 billion VND compared to September 30. Through review, 7 units disbursed higher than the average level; 12 units disbursed below the average level of the province.

Regarding the progress of implementing some key projects, some projects have had an increase in disbursement compared to the previous month. Typically, the Khanh Hoa - Buon Ma Thuot Expressway Project (Component 3) has disbursed over VND 3,078.5 billion, reaching 71.35% of the plan; the disbursed capital in 2025 increased by 5.57%. The Phu Yen Province Coastal Road Project, the section connecting Tuy An district - Tuy Hoa city (phase 1); the cumulative disbursement value to date is over VND 724.8 billion, the disbursed capital in 2025 increased by 23.9%. The Coastal Road Project, the section north of An Hai bridge, has disbursed nearly VND 97.36 billion of the planned capital in 2025, an increase of 2.35%...

Deputy Director of the Department of Finance Huynh Gia Hoang reported.
Deputy Director of the Department of Finance Huynh Gia Hoang reported on the progress of disbursement of public investment capital sources.

According to reports from departments and localities, the implementation of public investment capital disbursement still faces some difficulties and problems due to slow implementation of compensation, support and resettlement, mainly in determining the legality of land records; lack of resettlement land...

The implementation of some projects is still difficult due to the lack of earth quarries for some projects, and the shortage of construction sand supply. The planning of earth quarries for construction implementation is still slow; the price of construction materials in the western part of the province fluctuates, some detailed plans 1/500 are not suitable with the reality of socio -economic development...

In addition, due to the impact of the arrangement, consolidation and reorganization of the operating apparatus at all levels, some projects must make adjustments to extend contracts and review each capital source in detail before they can continue implementation...

The leader of the Department of Agriculture and Environment presented a report at the working session.
The leaders of the Department of Agriculture and Environment continued to present the work related to the department's field.

Concluding the meeting, Provincial Party Committee member and Vice Chairman of the Provincial People's Committee Truong Cong Thai acknowledged and highly appreciated the efforts of units and localities in implementing the task of disbursing public investment capital. Up to now, a number of problems have been gradually resolved; unit prices for crops have been issued, creating favorable conditions to promote compensation and site clearance (GPMB) to speed up the progress of project implementation.

To resolve difficulties and obstacles in the process of performing tasks, regarding the personnel issue of the staff working in the management of basic construction investment and compensation for site clearance, comrade Truong Cong Thai assigned the Department of Home Affairs to review and advise the Provincial People's Committee to supplement personnel at the commune and ward levels to carry out public investment management, deploy the field of natural resources and environment, project management, finance, planning, etc.; focus on implementing secondments and strengthening the commune level with department and branch officials with experience in implementing site clearance and implementing key projects.

Project Management Board leaders commit
The leaders of the Provincial Management Board of Investment in Construction of Traffic Works and Rural Development Agriculture pledged to disburse all assigned capital sources.

In order to promote the disbursement of public investment capital, localities proactively coordinate closely with relevant units to actively carry out procedures on site clearance to promptly hand over the site to the contractor for construction according to the project implementation schedule; completed projects must promptly complete the project acceptance documents...

Vice Chairman of the Provincial People's Committee Truong Cong Thai requested investors, project management boards, and departments assigned with capital to speed up the disbursement of capital in 2024; speed up the implementation of capital in 2025; review progress, encourage contractors to speed up the implementation of projects; prioritize compensation and site clearance capital, and create clean land to speed up the progress of projects.

The Department of Finance needs to regularly update the progress of public investment disbursement; review difficulties and problems to propose solutions to ministries and branches. The Department of Construction needs to pay attention to the progress of key projects being implemented in the province such as the North-South Expressway project, the coastal road, the Khanh Hoa - Buon Ma Thuot Expressway, the high-speed railway project; focus on reviewing the conditions for the commencement of the project of 3 schools in border communes.

Departments, localities, and project management boards need to proactively review and register public investment capital for the 2026-2030 period to be proactive and ready for the new period.

Source: https://baodaklak.vn/kinh-te/202510/thuc-day-giai-ngan-von-dau-tu-cong-uu-tien-giai-phong-mat-bang-bc10893/


Comment (0)

No data
No data

Same category

Vietnamese Films and the Journey to the Oscars
Young people go to the Northwest to check in during the most beautiful rice season of the year
In the season of 'hunting' for reed grass in Binh Lieu
In the middle of Can Gio mangrove forest

Same author

Heritage

Figure

Enterprise

Yen Nhi's national costume performance video has the highest views at Miss Grand International

News

Political System

Destination

Product