Vung Ang - Bung Expressway before the finish line

These days, investors, contractors, and supervision consultants are mobilizing maximum human resources and equipment to construct the final items to ensure the completion of the Vung Ang - Bung expressway project connecting Ha Tinh and Quang Tri provinces on August 19.

Báo Sài Gòn Giải phóngBáo Sài Gòn Giải phóng14/08/2025

Video : Vung Ang - Bung Expressway component project before the finish date

The Vung Ang - Bung expressway component project has a length of 55.34km, started in January 2023 with a total investment of about 12,540 billion VND, of which the section through Ha Tinh province is 12.9km long and the section through Quang Tri province is 42.44km long.

z6905039107046_c9b93a5bedc368331ab88a658fdca0b0.jpg
Engineers and workers are working hard on the construction site.

The project's starting point is at the Ky Hoa intersection in Ha Tinh province, connecting with the Ham Nghi - Vung Ang expressway; the end point is at Bo Trach commune in Quang Tri province, connecting with the Bung - Van Ninh expressway. According to the request of the Government and the Ministry of Construction , the Vung Ang - Bung expressway will be completed and open to traffic on August 19.

DJI_0038.JPG
Complete the final items to bring the project to the finish line on schedule

According to records, despite the extremely hot weather, high temperatures ranging from 37 to nearly 40 degrees Celsius, combined with the burning southwest wind (also known as Lao wind), hundreds of officers, engineers, workers of the investor, contractor, and consulting and supervising units are still working hard at the construction site with the spirit of "overcoming the sun and rain", working "3 shifts, 4 shifts" to determine to bring the project to the finish line.

DJI_0039.JPG
The final items of the Vung Ang - Bung expressway are being gradually completed.
DJI_0040.JPG

According to information from the Project Management Board (Project Management Board 6), the entire Vung Ang - Bung expressway is currently implementing 23 construction fronts simultaneously, with hundreds of machines and equipment and hundreds of officers, engineers and workers working continuously in many shifts.

The cumulative output value is equivalent to about 99% of the construction contract value. The unit is urging contractors and supervision consultants to focus on human resources, machinery and equipment to complete the remaining items, ensuring the opening of traffic on August 19.

DJI_0096.JPG
Carry out asphalt concrete pavement
DJI_0148.JPG

According to records, on 23 construction sites along the Vung Ang - Bung expressway, the working atmosphere was extremely urgent and bustling. The sound of machinery operating to complete the final items such as rolling, spreading asphalt concrete on the road surface... resounded throughout the construction site.

4I7A2931.JPG
Shape of Vung Ang - Bung expressway

On the Vung Ang - Bung expressway, contractors and construction units have installed guardrails, road markings, traffic signs, etc. in most sections.

DJI_0032.JPG
Many sections on the Vung Ang - Bung highway pass through hills, lakes, dams, and valleys.
DJI_0677.JPG

According to Mr. Hoang Xuan Thi (born in 1963, residing in Nghe An province, a worker constructing the Vung Ang - Bung expressway project), the terrain of the Vung Ang - Bung expressway project through Ha Tinh is complicated, the weather conditions are not favorable, especially in recent days the heat is very uncomfortable, combined with strong Lao winds, making it very difficult and tiring for people working on the construction site.

However, everyone tried their best to do well the tasks assigned by the investor and contractor, determined to ensure the project was completed on schedule. Everyone felt proud to contribute a small part of their efforts to the construction of the country's key traffic project.

4I7A2994.JPG
Engineers and workers work hard on the construction site.
DJI_0047.JPG

The Vung Ang - Bung expressway project through Ha Tinh province has many key overpasses crossing mountainous terrain, lakes, dams, rivers, streams and valleys through Ky Hoa and Ky Lac communes.

Now, after a long period of construction, the items have been basically completed. The area where these bridges will create a prominent highlight on the highway with charming and majestic natural scenery.

DJI_0988.JPG
Many overpasses over hills, valleys and dams on the Vung Ang - Bung highway
DJI_0703.JPG

In particular, the Vung Ang - Bung expressway also has the Deo But tunnel project located in the two communes of Ky Hoa and Ky Lac (Ha Tinh province). This is the only mountain tunnel and an important project on the North - South expressway section passing through Ha Tinh province.

4I7A3022.JPG
Deo But Tunnel on the Vung Ang - Bung expressway
DJI_0025.JPG

The Deo But tunnel project is nearly 1km long, with an investment capital of more than 1,000 billion VND, and is designed with 2 tunnel tubes 716m and 840m long.

Each tunnel is 15m wide, 8m high, has 3 lanes and expansion points to prevent incidents during use and an interior lighting system...

4I7A2876.JPG
Inside Deo But tunnel on Vung Ang - Bung expressway

Up to now, the Deo But tunnel and 4km of the main route have been completed by the contractor at about 98% of the volume, ensuring the smooth operation of the entire Vung Ang - Bung expressway project. The contractor is also trying to complete the remaining work.

DJI_0994.JPG
Deo But Tunnel on the Vung Ang - Bung expressway
DJI_0001.JPG

>> Image of Vung Ang - Bung expressway before completion:

DJI_0859.JPG
DJI_0002.JPG
DJI_0033.JPG
DJI_0036.JPG
DJI_0060.JPG
DJI_0032.JPG
DJI_0841.JPG
z6905040231768_5e712155df9dd9056610a9a431c29dd5.jpg
z6905044204321_d2257bbff0b26aecdbdac218641e16bd.jpg
z6905033587553_2a101e90857d8bdeae0444a4cd10d17a.jpg
z6905033156604_c1505f78727d8765ad9b5a56cb8a1dcd.jpg
z6905048146663_ee723fc2b548e03dc2ca77ab952f757d.jpg
z6905047694518_75550308cb83056f480eaf056d0441be.jpg
DJI_0132.JPG
DJI_0068.JPG
DJI_0079.JPG
z6905042878945_b5c609e4b21310431bf8ebe1de1cb098.jpg
DJI_0017.JPG
4I7A2898.JPG
va.jpg
DJI_0728.JPG
DJI_0755.JPG
DJI_0761.JPG

Source: https://www.sggp.org.vn/tuyen-duong-bo-cao-toc-vung-ang-bung-truoc-ngay-ve-dich-post808306.html


Comment (0)

No data
No data

Same tag

Same category

Hang Ma Street is brilliant with Mid-Autumn colors, young people are excitedly checking in non-stop
Historical message: Vinh Nghiem Pagoda woodblocks - documentary heritage of humanity
Admiring Gia Lai coastal wind power fields hidden in the clouds
Visit Lo Dieu fishing village in Gia Lai to see fishermen 'drawing' clover on the sea

Same author

Heritage

;

Figure

;

Enterprise

;

No videos available

News

;

Political System

;

Destination

;

Product

;