The route connecting Gia Binh Airport with Hanoi Capital is one of the projects allowed by the Government to be implemented according to the Resolution on special investment mechanisms and policies, which is of great significance in promoting the development of transport infrastructure, expanding urban space, creating momentum for socio -economic development of the province. This route has an expected cross-section of 120 m including: 10-lane main route, 4-lane side route with a total length of more than 27 km, passing through 8 communes and wards such as Trung Kenh, Luong Tai, Gia Binh, Lam Thao, Tram Lo, Mao Dien, Thuan Thanh, Tri Qua.
![]() |
People of Ca Dong Coi residential group declare the land area subject to recovery. |
According to the Plan issued by the Provincial People's Committee, the resettlement work serving the project is assigned to the People's Committee of Thuan Thanh Ward to preside over implementation. The project includes two main items: Construction of resettlement areas and renovation and expansion of cemeteries to serve the relocation of graves. In particular, the resettlement area must be completed before July 21, 2026, ensuring stable housing for households subject to relocation. As for the cemetery item, the completion deadline is before January 2, 2026, with the goal of striving to complete before the Winter Solstice. Thuan Thanh Ward is actively coordinating with relevant units to synchronously deploy, ensuring progress according to the set requirements.
The resettlement project is being implemented at two locations: Ca Dong Coi residential group and lots 6, 7, 8, 9 of Lac Thu Bac and Lac Thu Nam villages with a total area of about 20 hectares. At Ca Dong Coi residential group, the site clearance work is being carried out methodically and on schedule. The Gia Thuan Regional Land Fund Development Center branch has completed the statistics, identified the agricultural land users, measured the current status and counted the graves. Currently, the map of the current land measurement is being made public as a basis for submission to the Department of Agriculture and Environment for approval. Through the actual survey, the people are very cooperative and agree to implement.
The route connecting Gia Binh Airport with Hanoi Capital has an expected cross-section of 120 m, including: 10-lane main route, 4-lane side route with a total length of more than 27 km, passing through 8 communes and wards such as: Trung Kenh, Luong Tai, Gia Binh, Lam Thao, Tram Lo, Mao Dien, Thuan Thanh, Tri Qua. |
According to comrade Vuong Van Phuc, Head of the Ca Dong Coi residential group, the project has a scale of more than 7 hectares, requiring the recovery of residential land and agricultural land of more than 300 households. The residential group officials have propagated and mobilized people to come and declare and coordinate to publicly disclose the area at the cultural house so that everyone can clearly understand the information. Thanks to the consensus and response of the people, the implementation process has gone smoothly. Mr. Nguyen Cong Hoan, a household in the group, said: "My family has 1,200 square meters of agricultural land in the Dang Gia field, Cong Dau, which is subject to recovery. Knowing that opening a large road will bring common benefits to the community, as soon as I received the notice, I proactively declared and joined hands to create conditions for the site clearance work to be implemented quickly."
At the resettlement area of lots 6, 7, 8, 9 with an area of about 13 hectares, the site clearance work is also being actively implemented. Up to now, the consulting unit, Dong Duong Construction Joint Stock Company, has completed the statistics, identified the agricultural land users, counted the graves on the land and publicly announced the recovered area and compensation level to each household. Ms. Nguyen Thi Khien, a household subject to relocation, shared: "My family lives in a small alley with narrow roads. Now the State has opened a road, most of the old houses will be within the road construction area. Being moved to the new resettlement area, I am very happy because there are spacious roads and synchronous infrastructure." According to Ms. Khien, the family has completed the procedures for handing over the site and hopes that the project will be implemented soon so that people can stabilize their lives.
Each resettlement area includes essential infrastructure such as: Electricity, roads, schools, stations, auxiliary works... to ensure people live conveniently in their new place. Therefore, the ward carries out many procedures in parallel. The approval of the planning task has been completed; the opinions of the Department of Construction, relevant agencies, units, and the community are being collected as a basis for the appraisal and approval of the 1/500 detailed planning. According to the representative of the leader of Thuan Thanh ward, this is one of the projects implementing a special policy mechanism, the province has included in the "24-hour Green Channel" in handling administrative procedures. In the coming time, the ward will take the lead in coordinating the implementation of the following contents: Preparing, appraising, and approving the environmental impact assessment report, expected to be completed in early November 2025; Prepare, appraise, and approve construction drawing design documents and estimates in December, striving to hand over land to people for housing construction before January 30, 2026, earlier than planned.
Along with the construction of the resettlement area, Thuan Thanh ward is urgently implementing the cemetery expansion project to serve the relocation of graves for people in the planning area. Up to now, the locality has completed the steps of statistics, identifying land users, measuring the current status and is editing the land measurement map to submit to the competent authorities for approval. According to the plan, the selection of contractors and construction of technical infrastructure will be carried out in early January 2026.
Thus, the resettlement work serving the project of the route connecting Gia Binh Airport with Hanoi Capital is being implemented according to plan, relatively smoothly. The local government is making efforts to speed up the progress, shorten the implementation time so that people can soon move to new residences and stabilize their lives.
Source: https://baobacninhtv.vn/thuc-hien-du-an-duong-ket-noi-san-bay-gia-binh-thu-do-ha-noi-khan-truong-giai-phong-mat-bang-cac-khu-tai-dinh-cu-postid428804.bbg