According to the reporter of Tin Tuc and Dan Toc Newspaper, after a month of hydraulic jacking, the ball weighing more than 11,000 tons was raised 1.1 meters higher. This elevation helps ships to pass through the Saigon River more easily, reduces the risk of ship jams every time the tide rises and ensures safety for both roads and waterways.
According to the Road Traffic Infrastructure Management Center (Ho Chi Minh City Department of Construction), the clearance raising of Binh Trieu 1 Bridge has been completed as planned. Currently, the contractor has entered the phase of inspection, steel reinforcement, and bridge piers reinforcement. It is expected that by November 30, the bridge will be completed and the surface will be returned to traffic.
The project to raise the clearance of Binh Trieu 1 Bridge has a budget of 133 billion VND, starting from the end of 2024. From the end of August 2025, the bridge will limit car traffic for repairs. During this time, traffic at the eastern gateway of the city is often congested during rush hour.
Source: https://baotintuc.vn/anh/tp-ho-chi-minh-cau-binh-trieu-1-da-hoan-tat-nang-cao-them-11m-cuoi-thang-11-thong-xe-20251002084246083.htm
Comment (0)