The 850 billion VND bridge is behind schedule because of a land plot blocking the way.

Báo Giao thôngBáo Giao thông21/02/2025

The progress of the Tra Khuc 3 bridge project ( Quang Ngai ) has been seriously affected because a plot of land is blocking the construction site, even though the local government has worked many times to resolve the issue.


A plot of land of more than 1,000 square meters lies across a key project.

After more than 2 years of construction, Tra Khuc 3 Bridge has basically completed many items with construction value reaching over 90%. However, up to now, the compensation and site clearance work of the project has not been completed as on the North bank of Tra Khuc River there is still a plot of land blocking the bridge abutment.

Quảng Ngãi: Cầu 850 tỷ đồng chậm tiến độ vì thửa đất chắn ngang- Ảnh 1.

The 850 billion VND bridge project's progress was seriously affected due to a single plot of land.

It is noted that the uncleared land plot has a cross-section of about 25m, located in the middle of the road leading to the bridge, about 40m from the bridge abutment. On the current land plot, the landowner plants many types of trees such as acacia, eucalyptus, banana...

According to the compensation records, the above land plot belongs to the household of Mrs. Nguyen Thi Lien (deceased) and Mr. Huynh Ngoc Khanh (representative of the heirs), belongs to plot 49, area 1,106.6m2, including residential land and land for growing annual crops.

To resolve the issue of handing over the site to the contractor, Son Tinh district has held many meetings with Mr. Khanh’s family. They even held dialogues to resolve the problem. However, after nearly 2 years, Son Tinh district has not been able to complete the land acquisition for the construction of Tra Khuc 3 bridge project.

Quảng Ngãi: Cầu 850 tỷ đồng chậm tiến độ vì thửa đất chắn ngang- Ảnh 2.

The construction site for the bridge abutment and northern approach road is limited due to land acquisition problems, making the contractor tired.

Due to the land being blocked, the contractor's construction work has encountered many obstacles. To access the construction site, arrange mechanical equipment as well as transfer materials, the contractors have to negotiate with people whose land is outside the project to rent public roads.

The representative of the joint contractor said that the uncleared site has greatly affected the overall progress of the project. While the completion date for the project to be put into operation is approaching, the contractor hopes that the investor and local authorities will soon resolve the issue to complete the construction.

Completion of compulsory land acquisition in February 2025

Faced with the situation of land clearance hindering the progress of the hundred billion bridge project, Quang Ngai province organized many working sessions with the Management Board of investment and construction of traffic works, related localities and departments to direct and find solutions. However, after 2 years, all solutions have not been implemented.

To ensure a clean site for handover to the construction contractor, the People's Committee of Son Tinh district issued a decision to enforce land recovery for Mr. Khanh's household.

Quảng Ngãi: Cầu 850 tỷ đồng chậm tiến độ vì thửa đất chắn ngang- Ảnh 3.

Tra Khuc 3 Bridge has basically completed construction, currently the biggest bottleneck is the uncleared northern bridgehead.

Chairman of the People's Committee of Son Tinh District, Pham Xuan Vinh, said that the land acquisition for the Tra Khuc 3 Bridge project is very important. Many similar cases in the area have agreed to receive compensation and hand over the land. However, Mr. Khanh's family still does not agree.

"The district has issued a decision to enforce and reclaim the land. However, it still sends officials to continue to mobilize and persuade the landowner to agree to proactively hand over the land instead of having to enforce it according to regulations.

However, up to now, this household has not yet agreed to hand over the land. Therefore, based on the issued enforcement decision, the district will proceed with the compulsory land recovery. This is expected to be carried out on February 25," said Mr. Vinh.

It is known that the Tra Khuc 3 bridge project has an investment capital of 850 billion VND, spanning the Tra Khuc river connecting Tu Nghia and Son Tinh districts. The project started construction at the end of 2022, and is scheduled to be completed in the second quarter of 2025.

This is a key project monitored and directed by the Quang Ngai Provincial Party Committee. At the same time, it was chosen as the project to put up a welcome sign for the 21st Provincial Party Congress.

Quảng Ngãi: Cầu 850 tỷ đồng chậm tiến độ vì thửa đất chắn ngang- Ảnh 4.

Investors and contractors are hoping to have land to complete the project in the second quarter of 2025.

Speaking with Giao Thong Newspaper, Director of the Quang Ngai Traffic Construction Investment Project Management Board Ngo Van Dung said that most of the main items of the project have been completed.

The bridge abutment and northern approach road are stuck with site clearance, this is the biggest bottleneck making the contractor's efforts difficult.

According to Mr. Dung, if the site clearance is resolved, the contractor will speed up the construction to complete items such as roadbed embankment, aggregate embankment... because materials, machinery and equipment are ready.



Source: https://www.baogiaothong.vn/quang-ngai-cau-850-ty-dong-cham-tien-do-vi-thua-dat-chan-ngang-192250221194331699.htm

Comment (0)

No data
No data

Same tag

Same category

The beauty of Ha Long Bay has been recognized as a heritage site by UNESCO three times.
Lost in cloud hunting in Ta Xua
There is a hill of purple Sim flowers in the sky of Son La
Lantern - A Mid-Autumn Festival gift in memory

Same author

Heritage

;

Figure

;

Enterprise

;

No videos available

News

;

Political System

;

Destination

;

Product

;