The Tran Quoc Hoan - Cong Hoa connecting road project will start construction at the end of 2022, with a total investment of more than 4,800 billion VND. The main road is more than 4km long, 25 - 48m wide with 6 lanes, connecting two more branches of road 18E and C2 with 3 - 4 lanes wide.

In addition to the overpass in front of Tan Son Nhat Airport Terminal 3, the project also includes two underpasses at major intersections: Tran Quoc Hoan - Phan Thuc Duyen and Truong Chinh - Tan Ky Tan Quy.

Expected to be put into operation at the end of 2024, but difficulties in site clearance have caused the project to be delayed.

W-z6334586382604_eb66ed1178d247aba9c72489c9f20350.jpg
To date, the project has completed and put into temporary operation a 1.25 km long section (from Phan Thuc Duyen underpass to Hoang Hoa Tham street).
W-z6334586374662_5be75ea7dc55d7b8487e95664151846f.jpg
The 4-lane overpass in front of Terminal T3 has been completed. Currently, the remaining part of the route connecting Tran Quoc Hoan - Cong Hoa (from Hoang Hoa Tham Street to Truong Chinh Street) is under construction due to land clearance problems.

Talking to VietNamNet reporter, Mr. Le Huu Tuan - Deputy Head of Compensation and Site Clearance Board of Tan Binh District (HCMC) said that up to now, the land clearance problems have been resolved.

"Today, the last house in the alley of Tran Van Du street will be completely demolished and handed over to the investor," Mr. Tuan informed.

Meanwhile, Mr. Luong Minh Phuc - Director of the HCM City Traffic Works Management Board (Investor) confirmed that after receiving the site from Binh Tan district, contractors will speed up construction progress to open the entire route to traffic before the April 30 holiday.

W-6605.JPG.jpg
The last house in the alley of Tran Van Du street is being demolished for items within the project's scope of influence. Currently, the owner has finished dismantling to hand over the site to the investor.

W-6689.JPG.jpg
After much effort, Tan Binh District authorities have resolved the site clearance issues at Package 13 of the connecting road. At the construction site, the contractor is working vigorously to meet the schedule of clearing the entire route before the April 30 holiday.
W-6633.JPG.jpg
Construction area of ​​road, retaining wall, sidewalk, drainage, traffic organization at the intersection of Hoang Hoa Tham street with the overpass ramp of Tan Son Nhat airport terminal T3.
W-6673.JPG.jpg
After dismantling the site to hand over to the investor to implement the project, people are busy renovating their houses.
W-6674.JPG.jpg
The entire connecting road project passing through Tan Binh district has 85 affected cases, including 68 households, 17 units and organizations. The total recovered land area is more than 133,234m2.
W-6687.JPG.jpg
Once completed, the route will connect directly to Terminal T3 of Tan Son Nhat Airport (expected to be operational on April 30, 2025), creating a new approach to the airport, reducing pressure on the main entrance on Truong Son Street.
W-6663.JPG.jpg

In addition to speeding up the construction progress of the Tran Quoc Hoan - Cong Hoa connecting road, the investor is currently requesting the People's Committee of Tan Binh District to urgently complete the A41 canal renovation project. This is an important project to help connect the project's drainage system, ensuring the drainage capacity for Tan Son Nhat airport and T3 terminal, avoiding flooding.

Two traffic projects to prevent traffic congestion in Tan Son Nhat opened

Two traffic projects to prevent traffic congestion in Tan Son Nhat opened

Expanding Hoang Hoa Tham Street and the Tran Quoc Hoan - Cong Hoa connecting road are two key projects that will open to traffic on the occasion of Tet At Ty 2025, helping to reduce congestion at Tan Son Nhat gateway.
The road worth over 4,800 billion VND connecting Tan Son Nhat airport still has 22 problems

The road worth over 4,800 billion VND connecting Tan Son Nhat airport still has 22 problems

The Tran Quoc Hoan - Cong Hoa road project with a cost of more than 4,800 billion VND connecting Tan Son Nhat airport's T3 terminal still has 22 land issues.
Construction of Tan Son Nhat Airport Terminal 3 to be completed in the next 90 days

Construction of Tan Son Nhat Airport Terminal 3 to be completed in the next 90 days

Up to now, Tan Son Nhat Airport Terminal 3 has completed 83% of the construction volume. The contractor consortium will strive to complete the project in the next 90 days.