42 bridge girders, each weighing 80 tons, are placed on the spans by the contractor and are expected to be completed by the end of this year.
After more than a year of construction (October 15, 2023), at noon on December 17, Truong Son Construction Investment Joint Stock Company, one of the contractors constructing Dai Ngai 2 Bridge, organized the construction of the bridge girders at the project.
Clip of 42 bridge girders, each girder weighs 80 tons of Dai Ngai 2 bridge project.
During the construction, many engineers, workers, machines, equipment... were mobilized to support the bridge beams from the bank in An Thanh Tay commune, Cu Lao Dung district ( Soc Trang province) extending to the Hau river.
Mr. Tran Phong Vu, commander of Truong Son Construction Investment Joint Stock Company, said: "Our unit is responsible for the bridge section on the Hau River bank in An Thanh Tay commune, about 250m long.
We installed a total of 42 beams, each weighing about 80 tons. It is expected that all will be installed by the end of December 2024."
Dai Ngai 2 Bridge will have a total of 91 girders, each girder weighs 80 tons and is 40m long.
According to the documents, Dai Ngai 2 bridge is 862m long, with a total of 13 spans, with 91 bridge girders (each girder weighs more than 80 tons, nearly 40m long), the main span alone is 330m long and is constructed in a cantilever structure.
According to information from Project Management Board 85 ( Ministry of Transport , investor), the entire Dai Ngai Bridge project (including Dai Ngai 1 and Dai Ngai 2) has so far achieved about 53% of the volume of the packages. Of which, Dai Ngai 1 Bridge connecting Tra Vinh province with Soc Trang was started on December 9.
It is expected that Dai Ngai 2 Bridge will be completed before the Lunar New Year 2025 and put into use in 2025.
Dai Ngai 2 Bridge crosses the Hau River. The bridge is located in the area adjacent to Tran De estuary, connecting Cu Lao Dung district with the mainland, breaking the isolation of this land in the middle of the Hau River.
A T-beam waiting to be placed on the span.
The Dai Ngai Bridge Project (including Dai Ngai 1 and Dai Ngai 2) on National Highway 60 in Tra Vinh and Soc Trang provinces was approved for investment by the Ministry of Transport in Decision No. 1703/QD-BGTVT dated December 23, 2022.
This is a group A project, a special-grade road traffic project with a total investment of VND 7,962,148 billion, funded by the state budget.
The project has a total route length of about 15.14km, starting at the intersection with National Highway 54, in Hung Hoa commune (Tieu Can district, Tra Vinh province); ending at the intersection with Nam Song Hau national highway, in Long Duc commune (Long Phu district, Soc Trang province).
Heavy machinery and equipment lifted the 80-ton bridge girder onto the span.
The project includes two main bridge works (Dai Ngai 1 and Dai Ngai 2 bridges) fully invested with four lanes, the investment route is divided into phases with phase one including two lanes with a cross-section width of 12m, design speed of 80km/h, high-class A1 road surface.
Source: https://www.baogiaothong.vn/gac-42-dam-cau-dai-ngai-2-noi-cu-lao-dung-voi-quoc-lo-nam-song-hau-192241217140919981.htm