Due to the impact of storm No. 3, the power grid in the area was severely damaged, leading to power outages in all localities.
According to statistics of Quang Ninh Electricity Company, as of 8:00 a.m. on September 8, 50/59 110kV lines were out of operation. Currently, the Company has restored 9 lines, while 50/59 lines have not been energized. Among them, there was a serious incident of the 22kV pole falling at DZ 173, 174T500, the branch of the 110kV substation broke the pole. Today, the Company will handle and fix the remaining lines.
For 110kV transformer stations, the Company has energized 8 substations, of which 7/21 are assets of the Electricity Company and 1/9 110kV substations are assets of customers. Specifically including: 110kV substations E5.41 Dam Ha; E5.5 Cam Pha; E5.6 Tien Yen; E5.7 Mong Cai; E5.19 Hai Ha; E5.23 Trang Bach; E5.42 Dam Ha; E5.24 Texhong.

Regarding medium voltage lines, the Company has energized 12/180 medium voltage lines, mainly in Mong Cai area. Currently, the Company is directing the inspection of the remaining lines, ensuring that they are qualified to restore operation, prioritizing power supply to important customers.
Mr. Dang Thanh, Deputy Director of Quang Ninh Electricity Company said: Today, the Company will try to restore power to the central area of Hon Gai and the entire Bai Chay area of Ha Long City. Other localities will partially restore power.
Hoang Nga