Traffic regulation and diversion on Vo Nguyen Giap Street to serve the construction of the intersection between this road and Bien Hoa - Vung Tau Expressway will be implemented from 10:00 p.m. on September 5, 2025. Photo: Pham Tung |
Accordingly, based on the construction permit for the connecting intersection and on-site inspection of the traffic regulation plan to serve the installation of girder span No. 2 of branch bridge N0, at the intersection of Bien Hoa - Vung Tau expressway and Vo Nguyen Giap street, the Provincial Construction Investment Project Management Board announces the traffic regulation plan and time for construction.
Specifically, traffic regulation and diversion on Vo Nguyen Giap Street to serve the construction of the above project will be carried out in 2 sessions: from 10:00 p.m. on September 5, 2025 to 5:00 a.m. on September 6, 2025; from 10:00 p.m. on September 6, 2025 to 5:00 a.m. on September 7, 2025.
During the time of traffic regulation and diversion for construction, vehicles traveling on Vo Nguyen Giap Street in the direction of Ho Chi Minh City to the construction area (Km1861+138 according to Vo Nguyen Giap Street's route) will be diverted to GT1 branch (road surface width 11m) to go around the construction area and connect with Vo Nguyen Giap Street, moving towards Ho Chi Minh City according to the route.
For vehicles traveling on Vo Nguyen Giap Street towards the old Trang Bom district, when reaching the construction area (Km1862+010 according to Vo Nguyen Giap Street's route), turn left onto GT1 Street, go around the construction area and connect to Vo Nguyen Giap Street to move towards the old Trang Bom district according to the route.
The intersection between Vo Nguyen Giap Street and Bien Hoa - Vung Tau Expressway belongs to Component 1 of Bien Hoa - Vung Tau Expressway Project. This is one of the large intersections with complex construction. According to the Provincial Construction Investment Project Management Board, this intersection has completed 65% of the construction volume, completed the overpass piers and ensured the installation of girders. Contractors are speeding up the progress and completing this item to ensure synchronization with the entire project, achieving the goal of technical traffic opening of the project before December 19, 2025 as required by the Prime Minister .
Pham Tung