The first barge carrying sea sand arrived at the highway construction site in Ca Mau.

Báo Giao thôngBáo Giao thông10/07/2024


As of May 23, 2024, the total construction output value of the Can Tho - Ca Mau expressway project reached about 29%.

Contractors have mobilized 64 sand pumps for the project (of which, Can Tho - Hau Giang section has 23 pumps; Hau Giang - Ca Mau section has 41 pumps). The current average capacity of a pump is about 1,005m3/day.

It is expected that by October 30, the project will need to mobilize 11.2 million m3, with an exploitation capacity of 67,000 - 73,000 m3 of sand/day.

The Can Tho - Ca Mau Expressway project started construction on January 1, 2023, with a length of more than 110km and a total investment of more than VND 27,500 billion.

The project is divided into two component projects: Can Tho - Hau Giang component project has a length of more than 37km, total investment of more than 10,370 billion VND; Hau Giang - Ca Mau component project has a length of more than 73km, total investment of more than 17,152 billion VND.



Source: https://www.baogiaothong.vn/sa-lan-cho-cat-bien-dau-tien-ve-den-cao-toc-o-ca-mau-19224071013351307.htm

Comment (0)

No data
No data

Same tag

Same category

Visit Lo Dieu fishing village in Gia Lai to see fishermen 'drawing' clover on the sea
Locksmith turns beer cans into vibrant Mid-Autumn lanterns
Spend millions to learn flower arrangement, find bonding experiences during Mid-Autumn Festival
There is a hill of purple Sim flowers in the sky of Son La

Same author

Heritage

;

Figure

;

Enterprise

;

No videos available

News

;

Political System

;

Destination

;

Product

;