Prime Minister requests basic completion of Long Thanh Airport project by December 2025

Prime Minister Pham Minh Chinh asked the investor to speed up construction progress to basically complete Long Thanh Airport by December 19, 2025, and move towards commercial operation in early 2026.

Báo Đầu tưBáo Đầu tư29/12/2024

On the afternoon of August 2, in Dong Nai , Prime Minister Pham Minh Chinh inspected the construction progress of the Long Thanh International Airport Project. This was the 8th time the Prime Minister inspected the construction progress of this Project.

Reporting to the Prime Minister on the progress up to now, Vietnam Airports Corporation (ACV) said that currently the entire component project 3 ( essential works in the airport with a total investment of 99,000 billion VND ) has 14 packages, of which 3 packages have been completed and the remaining 11 packages are under construction.

Up to now, the total volume value has reached 50.73% of the signed contract value.

As for the construction of the passenger terminal, 4,700 personnel and more than 1,000 machines and equipment are currently being arranged to carry out the construction. Up to now, 99% of the steel roof structure has been completed and the entire central roof structure is expected to be completed before August 15, 2025.

Prime Minister inspects construction progress of Long Thanh Airport's second runway - Photo: VGP

For runway 1, it has been basically completed. As for runway 2, ACV started construction on May 30, 2025.

After listening to the reports of the units, Prime Minister Pham Minh Chinh commended relevant agencies such as the Ministry of Construction and ACV for completing many tasks.

However, the Prime Minister said that there is still a lot of work to do from now until the end of the year to achieve the goal of basically completing the Project by December 19, 2025, moving towards commercial exploitation in early 2026.

To achieve this goal, the Prime Minister directed the Ministries, branches, People's Committees of Ho Chi Minh City, Dong Nai province, investors, contractors... to try harder, to try harder to complete the Project.

With the spirit of speed, boldness, only talking about work, no backtracking, overcoming the sun, overcoming the rain, not losing to storms, working in 3 shifts, 4 teams, working through holidays, Tet, and days off, the Prime Minister requested the agencies to rebuild the progress critical path according to the set goals, clearly assigning people, work, time, responsibility, results, and authority, and strengthening supervision, inspection, and monitoring.

The Prime Minister especially noted that investors must complete on schedule while ensuring quality, technical requirements, aesthetics, safety, and environmental sanitation.

On the same evening, Prime Minister Pham Minh Chinh inspected the construction progress of the Ho Chi Minh City Ring Road 3 Project, Tan Van - Nhon Trach section.

According to the report of the Ministry of Construction, the 8.22 km long Ring Road 3 section Tan Van - Nhon Trach (connecting Ho Chi Minh City with Dong Nai) has reached nearly 98% progress. The project will be opened to traffic on August 19.

Here, the Prime Minister gave gifts and encouraged the team of officers, engineers, workers and laborers at the construction site.

The Prime Minister also commended the Ministry of Construction, the My Thuan Project Management Board (under the Ministry of Construction) and localities for completing the Nhon Trach Bridge 1.5 months ahead of schedule to put it into operation, reducing travel and logistics costs for people and businesses.

Source: https://baodautu.vn/thu-tuong-yeu-cau-co-ban-hoan-thanh-du-an-san-bay-long-thanh-vao-thang-122025-d347268.html


Comment (0)

No data
No data

Same tag

Same category

Re-enactment of the Ly Dynasty's Mid-Autumn Festival at Thang Long Imperial Citadel
Western tourists enjoy buying Mid-Autumn Festival toys on Hang Ma Street to give to their children and grandchildren.
Hang Ma Street is brilliant with Mid-Autumn colors, young people are excitedly checking in non-stop
Historical message: Vinh Nghiem Pagoda woodblocks - documentary heritage of humanity

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product