Delegates performed the ceremony of attaching the signboard of the 110kV Tuyen Quang 2 Transformer Station, My Lam Ward (Tuyen Quang City).
The Tuyen Quang 2 110kV Power Line and Substation Project has a scale of nearly 1 hectare with an operator house, 2 40MVA transformers, 50m of 110kV power line, a camera monitoring and remote control system, automatic fire prevention and fighting, according to the criteria of an unmanned substation. This is the first digital 110kV substation in the Northern Midlands and Mountains provinces, managed and operated by Tuyen Quang Electricity Company, with a total investment of over 76 billion VND.
The project contributes to improving transmission capacity, meeting the demand for load development, strengthening grid connectivity, and improving the reliability of power supply in My Lam tourist area and part of Yen Son district and Tuyen Quang city.
Source: https://baotuyenquang.com.vn/dong-dien-va-gan-bien-cong-trinh-tram-bien-ap-110kv-tuyen-quang-2!-204361.html